Marketing/Billion Downloads campaign postmorterm: Difference between revisions
Jump to navigation
Jump to search
No edit summary |
(→Issues) |
||
| Line 28: | Line 28: | ||
= Issues = | = Issues = | ||
* QA was approached late | |||
** This made us rush | |||
** We didn't know about bit.ly, and tested functionality, which worked on the surface, but the bit.ly links were broken, as William discovered | |||
** Weights and measures (metric, etc.) caused confusion | |||
= Concerns = | = Concerns = | ||
= How we can improve = | = How we can improve = | ||
Revision as of 18:08, 5 August 2009
Teams involved
- Marketing
- IT
- WebDev
- QA
- l10n
- PR
Timeline
Original launch date: mid-August
Actual launch date: July 31st (2 weeks early)
Changes to the timeline
Decision to launch on August 3rd
Decision to push launch to July 31st
What worked well
Issues
- QA was approached late
- This made us rush
- We didn't know about bit.ly, and tested functionality, which worked on the surface, but the bit.ly links were broken, as William discovered
- Weights and measures (metric, etc.) caused confusion