Below is a weekly engineering development update.
Below is a weekly engineering development update.
<p> </p>
<p> </p>
==== July 9 Update ====
==== July 16 Update ====
<p> </p>
<p> </p>
* Status: '''Green''' - In Development.
* Status: '''Green''' - In Development.
* Team is [https://mzl.la/2GoDoCJ currently working on Iteration #8] which runs from July 9 - July 20.
* Team is [https://mzl.la/2GoDoCJ currently working on Iteration #8] which runs from July 9 - July 20.
* A cumulative completion of 46 bugs is required by the conclusion of Iteration #8 to remain on schedule.
* A cumulative completion of 46 bugs is required by the conclusion of Iteration #8 to remain on schedule.
* Team has, to date, a cumulative completion of 42 bugs for Iteration #8.
* Team has, to date, a cumulative completion of 44 bugs for Iteration #8.
* Team has [https://mzl.la/2HyVqTB completed 84%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog].
* Team has [https://mzl.la/2HyVqTB completed 87%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog].
* The forecast completion of the entire Milestone 1 - 3 Backlog is on August 17.
* The forecast completion of the entire Milestone 1 - 3 Backlog is on August 17.
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog.
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog.
[[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Monday, July 9.]]
[[File:WPD CurrentUpdateNow.png|frame|center|Updated Weekly. Current Update - Monday, July 16.]]
<p> </p>
<p> </p>


Confirmed users
4,174

edits