| Line 19: | Line 19: | ||
* A cumulative completion of 46 bugs is required by the conclusion of Iteration #8 to remain on schedule. | * A cumulative completion of 46 bugs is required by the conclusion of Iteration #8 to remain on schedule. | ||
* Team has, to date, a cumulative completion of 44 bugs for Iteration #8. | * Team has, to date, a cumulative completion of 44 bugs for Iteration #8. | ||
* Team has [https://mzl.la/2HyVqTB completed | * Team has [https://mzl.la/2HyVqTB completed 86%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog]. | ||
* The forecast completion of the entire Milestone 1 - 3 Backlog is on August 17. | * The forecast completion of the entire Milestone 1 - 3 Backlog is on August 17. | ||
* View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog. | * View [https://docs.google.com/spreadsheets/d/19ZsqjD_H4fOjg7iPKBsMQ_toM1ywAvvd5hqvI0p1QGI/edit?usp=sharing Project Tracking Dashboard] for current schedule progress and backlog. | ||