** Release schedule
*** Code freeze (for blockers): Apr 30
*** Registration server code complete: Need date from Les*** String Freeze: Apr 30?
*** H/W set up complete and configured: May 5
*** Load testing done : May 13
*** l10n complete: ?May 11
*** Security reviews done: May 10
*** RC release date: May 12*** QA release sign off: May 13
*** Unit tests for Primary done: May 10
*** RC release dateWeb content finalized and staged: May 1413*** PR/Announcement complete and finalized: May 13
*** GA date: May 17, 2010
* Thick client testing is not 1.3 blocker.
* uTest contracts are in legal review.
*May 17 production migration checklist (owner: zandr)* Marketing plan is going to be slowly ramped up, so we can dial up/down based on feedback. Also expecting the iPhone client to help get users.* iPhone client project page: https://intranet.mozilla.org/Mobile/iPhoneWeaveClient1.0