IT/Production Acceptance/Retention
< IT | Production Acceptance
Start of project
Name each of the following:
- Project sponsor: D.Ronitzky
- Main IT contact: J.Fitzhugh
- Main WebDev contact: M.Morgan
- Main QA contact: S.Donner
- Main third party contact (if developed externally): AKQA (retention agency); James DeJesus (james.dejesus@akqa.com)
- Final application owner/maintainer: D.Rolnitzky
Overall goal of the project
- Improve Firefox Retention by creating a micro site where users can share a video with friends and family (fightagainstboredom.org)
Any pre-requisites needed (technology, server capacity, staffing, monitoring, response time, etc):
- Goal is to have project up and running by week of 12/24/07
- Domain name "fightagainstboredom.org" purchased -- done
- Access to SVN needed -- done (see bug 403504)
- Staging server required -- done (see bug 408402)
- Urchin analytics needed on micro site -- in progress (bug 408932)
- Email relay information needed for send-to-a-friend functionality -- in progress (bug 408894)
Initial timeline
- Development week of 12/17/07
External dependencies
- AKQA development time, Mozilla creative signoff and approval, video production
Dev environment specs
- Need email-to-a-friend functionality, including captcha to prevent/reduce spam
Staging Signoff
In order to get an app into staging, the following should be completed:
- Code committed to Mozilla source control and tagged
- Initial architecture review by IT and WebDev
- Site must be password protected
- Review timeline to go live
- Review any production requirements so IT can order any new hardware needed
Production Signoff/Launch
- Final WebDev signoff
- Final IT signoff
- Final QA signoff
- Operations documents filled for support & any training complete
- Monitors in place