QA/Weave Test Plan/1.3: Difference between revisions
< QA | Weave Test Plan
Jump to navigation
Jump to search
m (→Schedule) |
|||
Line 12: | Line 12: | ||
== Schedule == | == Schedule == | ||
* QA starts: ? | * QA starts: ? | ||
* Functional Tests: 1-2 persons (three days): | * Functional Tests: 1-2 persons (three days): | ||
** Primary Platforms | ** Primary Platforms | ||
* Large Profile First Sync testing | * Large Profile First Sync testing |
Revision as of 20:28, 13 April 2010
Weave 1.3 Test Plan
Manual test plan of 1.3. Focus on functional testing and large profile initial sync to ensure high quality user experience and no data loss
Description of Release
Point release with mainly fixes for usability and performance. Weave Update page
Current Tasks
- Flesh out FFT's and test plan
- Verify fixed blocking and targeted bugs (translates to P1/P2 though not flagged that way)
- Set up test day for 4/23
Schedule
- QA starts: ?
- Functional Tests: 1-2 persons (three days):
- Primary Platforms
- Large Profile First Sync testing
- Primary Platforms
- Release ?
Builds
Test Results
- FFT's - tbd
- Exploratory - tbd
Bugs Filed
Please add whiteboard note [weave1.3] to generate this Bugs found in weave1.3 list.