Firefox:1.5.0.8:Schedule: Difference between revisions

From MozillaWiki
Jump to navigation Jump to search
mNo edit summary
 
No edit summary
 
(7 intermediate revisions by the same user not shown)
Line 2: Line 2:


'''Development:'''
'''Development:'''
* '''RC6 Available:''' Saturday 9/9 (Firefox + Thunderbird)
*'''Note:''' Dates tentative and depending on relese of 2.0
* '''Tentative Ship Dates:''' Thursday 9/14 (Firefox + Thunderbird)
* '''RC1 Available:''' One day after 2.0release, Wednesday, October 25
<font color=lightgray>
* '''Tentative Ship Dates:''' Tuesday, November 7th
* '''Nominations Deadline:''' Tuesday, August 15th
* '''Nominations Deadline:'''  
* '''Patch Approval Request Deadline:''' Tuesday, August 22nd
* '''Patch Approval Request Deadline:'''  
* '''Code Freeze (Checkin Deadline):''' Friday, August 25th
* '''Code Freeze (Checkin Deadline):'''  
* '''First Candidates Available:''' Tuesday, August 29th (Firefox); Wednesday, August 30th (Thunderbird)
* '''First Candidates Available:''' Tuesday, October 17 (Firefox)
</font>


'''QA (RC6, FF + TB):'''
'''QA:'''
* '''Smoketests:''' Monday 9/11
* '''Bug Verifications:''' Ongoings starting Tuesday, October 17
* '''Post to the QA blog for Community Testing:''' Monday 9/11
* '''Smoketests:''' Wednesday, October 25
* '''Focus/Exploratory Testing:''' Monday 9/11 - Tuesday 9/12
* '''BFTs:''' Wednesday, Thursday, October 25, 26
* '''l10n + Update Testing:''' Tuesday 9/12 - Wednesday 9/13
* '''Post to the QA blog for Community Testing:''' Tuesday, October 31
* '''Focus/Exploratory Testing:''' Thursday, Friday, November 2, 3
* '''l10n + Update Testing:''' Monday, November 6th
* '''Live Update Testing:''' Tuesday, November 7th
* '''Special Distro Spotchecks:''' Thursday, Friday, Monday, November 10, 11, 13
* '''Special Distro Updates Checks:''' Tuesday, Wednesday, November 14, 15


'''Release (RC6, FF + TB):'''
'''Release:'''
* '''RC6 builds:''' Saturday 9/9 (enUS)
* '''RC1 builds:''' Wednesday, October 25
* '''l10n builds:''' Monday 9/11
* '''l10n builds:''' Friday, October 27
* '''Update Patches/CJK Repackaging:''' Tuesday 9/12 - Wednesday 9/13
* '''Notify Partners and Distributors of final RC:''' Basil, Monday, November 6th
* '''Notify Partners and Distributors of final RC:''' Basil 9/13
* '''Prep Security Notes and Notify Security Group:''' Monday, November 6th
* '''Prep Security Notes and Notify Security Group:''' Dan 9/12
* '''Release Signing + Staging:''' Monday, November 6th
* '''Release Signing + Staging:''' Wednesday 9/13
* '''Final Release:''' Tuesday, November 7th
* Final Release: Thursday 9/14
* '''Special Distro Repackaging:''' Wednesday, Thursday, Friday November 8, 9, 10
 
* '''Special Distro Release:''' Thursday, November, 16
<font color=lightgray>
'''QA (RC1 - RC5):'''
* '''Bug Verifications:''' Ongoing starting Monday, August 14th
* '''Smoketests:''' Tuesday, August 29th
* '''BFTs:''' Tuesday, August 29th - Wednesday, August 30th
* '''Post to the QA blog for Community Testing:''' Wednesday, August 30th
* '''RC1/Community Testing and Test Day:''' Friday, September 1st
* '''Focus/Exploratory Testing:''' Ongoing starting Tuesday, August 29th
* '''l10n + Update Testing:''' Tuesday, September 4th - Wednesday, September 5th
* '''Thunderbird QA'''
** Smoketests: Tuesday, September 5th
** BFTs: Tuesday, September 5th - Thursday, September 7th
** l10n + Update Testing: Friday, September 8th - Tuesday, September 12th
** Verifications and Focus/Exploratory Testing: Ongoing staring Thursday, September 7th
 
'''Release (RC1 - RC5):'''
* Candidate Builds: [4.5] - Monday, Aug. 28 [Tuesday, August 29th] enUS
* l10n Packaging: [7.5] - Wednesday, Aug. 30 [Thursday, August 31st]
* Update Patches/CJK Repackaging: [11.5] - Thursday, August 31 afternoon
* Notify Partners and Distributors of final RC: Basil 8/31
* Prep Security Notes and Notify Security Group: Dan 8/31
* Release Signing: [9.5] - Thursday, September 7
* '''Thunderbird Build/Release'''
** Candidate Builds: Wednesday, August 30th
** l10n Packaging: Friday, September 8th
** Update Patches: Friday, September 8th - Monday September 11th
</font>

Latest revision as of 18:07, 7 November 2006

1.5.0.8 Schedule

Development:

  • Note: Dates tentative and depending on relese of 2.0
  • RC1 Available: One day after 2.0release, Wednesday, October 25
  • Tentative Ship Dates: Tuesday, November 7th
  • Nominations Deadline:
  • Patch Approval Request Deadline:
  • Code Freeze (Checkin Deadline):
  • First Candidates Available: Tuesday, October 17 (Firefox)

QA:

  • Bug Verifications: Ongoings starting Tuesday, October 17
  • Smoketests: Wednesday, October 25
  • BFTs: Wednesday, Thursday, October 25, 26
  • Post to the QA blog for Community Testing: Tuesday, October 31
  • Focus/Exploratory Testing: Thursday, Friday, November 2, 3
  • l10n + Update Testing: Monday, November 6th
  • Live Update Testing: Tuesday, November 7th
  • Special Distro Spotchecks: Thursday, Friday, Monday, November 10, 11, 13
  • Special Distro Updates Checks: Tuesday, Wednesday, November 14, 15

Release:

  • RC1 builds: Wednesday, October 25
  • l10n builds: Friday, October 27
  • Notify Partners and Distributors of final RC: Basil, Monday, November 6th
  • Prep Security Notes and Notify Security Group: Monday, November 6th
  • Release Signing + Staging: Monday, November 6th
  • Final Release: Tuesday, November 7th
  • Special Distro Repackaging: Wednesday, Thursday, Friday November 8, 9, 10
  • Special Distro Release: Thursday, November, 16