=Photon Project Status Updates=
=Photon Project Status Updates=
<p> </p>
<p> </p>
==Tuesday, April 25, 2017==
==Tuesday, May 2, 2017==
<sub>''Note:  Updated every Tuesday.''</sub>
<sub>''Note:  Updated every Tuesday.''</sub>
<p> </p>
<p> </p>
Line 19: Line 19:
* Release 55 to date - [http://tinyurl.com/k79k3c8 view work].
* Release 55 to date - [http://tinyurl.com/k79k3c8 view work].
* Project Backlog to date - [http://tinyurl.com/l7lhk8h view work].
* Project Backlog to date - [http://tinyurl.com/l7lhk8h view work].
* Reserve Backlog to date - [http://tinyurl.com/k3mcbl6 view work].
* Completion to date - [http://tinyurl.com/k3cmwj3 view work].
* Completion to date - [http://tinyurl.com/k3cmwj3 view work].
* First release will be used to gather performance data in order to set the MVP release forecast.  
* First release will be used to gather performance data in order to set the MVP release forecast.  

Revision as of 14:22, 2 May 2017

Photon Project Status Updates

Tuesday, May 2, 2017

Note: Updated every Tuesday.

Project Tracking

Visual Redesign Team

  • In Development.
  • Release 55 to date - view work.
  • Project Backlog to date - view work.
  • Completion to date - view work.
  • First release will be used to gather performance data in order to set the MVP release forecast.
  • Release forecast and MVP Backlog to be set on Tuesday May 23.

Performance Team

  • In Development.
  • Release 55 to date - view work.
  • Project Backlog to date - view work.
  • Reserve Backlog to date - view work.
  • Completion to date - view work.
  • First release will be used to gather performance data in order to set the MVP release forecast.
  • Release forecast and MVP Backlog to be set on Tuesday May 23.

Structure Team

  • In Development.
  • Release 55 to date - view work.
  • Project Backlog to date - view work.
  • Completion to date - view work.
  • First release will be used to gather performance data in order to set the MVP release forecast.
  • Release forecast and MVP Backlog to be set on Tuesday May 23.

Animation Team

  • In Development.
  • Release 55 to date - view work.
  • Project Backlog to date - view work.
  • Completion to date - view work.
  • First release will be used to gather performance data in order to set the MVP release forecast.
  • Release forecast and MVP Backlog to be set on Tuesday May 23.

Onboarding Team

  • In Development.
  • Release 55 to date - view work.
  • Two more full-time ENG team members will join on May 1st.
  • First release will be used to gather performance data in order to set the MVP release forecast.
  • Release forecast and MVP Backlog to be set on Tuesday May 23.

Preference Team

  • In Development.
  • Release 55 to date - view work.
  • One more full-time ENG team member will join on May 1st.
  • First release will be used to gather performance data in order to set the MVP release forecast.
  • Release forecast and MVP Backlog to be set on Tuesday May 23.