Project Management/2012 Q1/Meetings/2012-02-17

From MozillaWiki
Jump to: navigation, search

Project Management Initiative Check-in - 2012-02-17

Attendees

  • cmore
  • ckoehler
  • malexis
  • bensternthal
  • jv

Previous Action Items

  • PM Team to reach out to teams who have submitted projects to prioritize them. DONE 70% converage.

Agenda

  • Input from Jim Cook
  • Next steps
    • Create list is only P1s and P2s from: https://intranet.mozilla.org/Projects/2012/Q1/Prioritized
    • Determine team (IT, QA, Security, Webdev, etc.) needs (High, Medium, Low, None) for each of those projects
    • Aggregate team needs
    • Reality check with the teams on if all of the P1s and P2s are possible.
    • Post sub-set of what is possible in the short term
    • Web Prod team is going to do a test run of Teambox 4 on real projects to determine if it is in or out.
    • Repeat process in March

Notes

  • Project needs: High, Low, None
  • Deadline for project needs: Feb 23rd

Action items

  • cmore to create spreadsheet with P1s and P2s and columns for team needs
  • Web prod team to fill in what they can and reach out to teams to gather more info.