Websites/Affiliates Facebook App/Weekly-Status-Reports/2012-07-05
From MozillaWiki
Contents
Summary
DOC VERSION: 1.0 | STATUS REPORT AS OF: July 05 2012 |
AUTHOR: Benjamin Sternthal |
TPM: Benjamin Sternthal |
PROJECT SPONSOR: Chelsea Novak |
PROJECT WIKI: Websites/Affiliates_Facebook_App |
Status
1. STATUS | |||||
Status Item | On Track | Caution | Crisis | N/A | Comment |
OVERALL STATUS | X | ||||
Schedule | X | ||||
Scope | X | ||||
Budget | X |
Schedule & Budget
2. SCHEDULE | |||
Start Date | Completion Date | ||
Original | Current | Original | Current |
June 11 | June 11 | 8/29 |
3. BUDGET | |||
Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
N/A | N/A | N/A | N/A |
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
5. UPCOMING TASKS | ||||
Task | Owner | Due Date | Bugzilla | Comments |
Milestone Approvals | BS/Team | |||
Tracker Bugs & Dev Bugs | BS/MK | |||
Finalize Wireframes | BS/Team | Complete |
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
Decide On Pursuing Ad API | CN | High | 6/25 | Resolved |
Project Milestones
7. PROJECT MILESTONES | |||||||
Issue | Owner | Target Completion Date |
Revised Completion Date |
Actual Completion Date |
Bugzilla | Status | |
WebDev | |||||||
Wireframes Final | BS | 7/5 | Complete | ||||
Ready To Test | MK | 8/17 | |||||
Live | MK | 8/29 | |||||
Design | |||||||
Designs 1st Round | TBD | TBD | |||||
Designs Final | TBD | TBD | |||||
Privacy/Legal | |||||||
Review | SM | Complete | |||||
L10N | |||||||
L10N Start | TBD | TBD | |||||
L10N Complete | TBD | TBD | |||||
QA | |||||||
Review | RB | 8/20 - 8/24 | |||||
Security | |||||||
Review | TBD | 8/20 - 8/24 | |||||
IT | |||||||
FB Dev Server | TBD | 7/13 | 772183 |