Websites/Markup/Meetings/2011-06-02
From MozillaWiki
This is the agenda and action items for the pre-launch check-in for Markup.
Contents
Time / Location
- Date: 2011-06-02
- Time: 8:30am PDT
- Room: All Your Base
- Conf: #329
- IRC#: irc.mozilla.org #markup
Agenda
GO!
The purpose of this meeting is to have check-in on the status of the Mark Up dark launch.
Status
Previous Action Items
- Michael C - Continue security testing.
- Brez - Fix https://bugzilla.mozilla.org/show_bug.cgi?id=659490
- Matt - Commence load testing.
- Matt - Send status update on Tuesday 5/31.
Updates
- TBG - Said they were all done.
- TBG has been very responsive in the past 24 hours.
- Matt
- Successfully submitted 3,000 fairly complex marks in 5 minutes.
- Will do more performance testing with JMeter
- Submitted duplicates; returned 200s.
- Will begin verifying the bugs and regression testing today.
- Site is not displaying properly in IE9; but only on some systems.
- Feeling good outside of the IE9
- Fred
- Fixed a number of issues
- Happy with perfomance
- Laura
- Admin panel does not work perfectly, but it works
- May file bugs for 1.1 milestone
- Realized that video of Evan mentions phase 2 and phase 3 - needs to get a new version of video
- Getting marketing pushes re-lined up
- Preference for a push on Tuesday and releasing announcement on Wednesday and snippets on Thursday
- Corey
- Asked Matt to re-run test against dev to figure out where it breaks.
- Stas
- We're good.
- Updated strings; will get those translated from last week.
- Infrasec
- Verified all videos
- Bugs
- 0 Bugs in Target Milestone 1.0 - http://bit.ly/isFryK
Action Items
- Laura - File bug to update video
- Fred - File bug to update stage
- Matt - Track down IE9 issues
- Matt - Begin regression testing and verification
- Stas - Continue L10N tasks
- Matt - Load test against stage for verification
- Corey - Will need to update production on Tuesday
- MPressman - Will need to update database by deleting existing marks or re-import / migrate data
- Laura - Schedule next meeting for go / no-go.
Next Meeting
Will setup an 8:30 meeting for Tuesday June 7.