Websites/ReMo Mozilla Reps/Weekly-Status-Reports/2012-06-11

From MozillaWiki
Jump to: navigation, search
Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: June 11, 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Pierros Papadeas
PROJECT WIKI: Websites/ReMo_Mozilla_Reps
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
May 30 2012 May 30 2012 R 0.3 TBD R 0.3 TBD
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Met with Rbillings about test plan, will start task the week of the 19th
  • Met with Mozillians about using API: 6/13 stage 6/20 live
  • Scoping of 0.3
  • 0.2.5 Launched
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
- - - - -
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
- - - - - -
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Actual
Completion
Date
Bugzilla Status
ReMo Team
  0.3 Ready To Test GL TBD
  0.3 Live GL TBD
Privacy/Legal
  Release 0.3 Review SM TBD XXX
QA
  Release 0.3 Review RB TBD XXX
Security
  Release 0.3 Review YB TBD XXX