==Erin==
==Erin==
*Q3 goals done
*Dynamic URL bar is ready!
*Getting product announcements tested
*FHR...
*Getting ready for GA release on 08/06
* <3


==Lawrence==
==Lawrence==
Line 22: Line 28:


==Marco==
==Marco==
* Iteration #11 ends on Friday July 26.
* Metro
* Team had a successful Iteration #10:  [https://wiki.mozilla.org/Firefox/Metro/Iteration10StatusReport View Status Report]
** Iteration #11 ends on Friday July 26.
* Working with Asa on developing a plan for a Metro Preview release.
** Team had a successful Iteration #10:  [https://wiki.mozilla.org/Firefox/Metro/Iteration10StatusReport View Status Report]
** Working with Asa on developing a plan for a Metro Preview release.
* Games
** Nexus 4 phones delivered to Hit Point and Disney to start testing WMW on FFOS.
** Regression testing for games has been setup.


==Sheila==
==Sheila==