Line 14: | Line 14: | ||
* Completed Gate 1 review on Tue Oct 4th with PIB. We passed! | * Completed Gate 1 review on Tue Oct 4th with PIB. We passed! | ||
**UX delivered out of box user journey wireframes | **UX delivered out of box user journey wireframes | ||
** Feedback to provide at next PIB status checkin: | ** Feedback to provide at next PIB status checkin: | ||
*** Provide more details project's critical path | *** Provide more details project's critical path | ||
Line 20: | Line 19: | ||
*** Completed initial legal review on project requirements for future Hardware ODM partnership to support program launch | *** Completed initial legal review on project requirements for future Hardware ODM partnership to support program launch | ||
* Initiate User Test in Taipei for late Oct. | * Initiate User Test in Taipei for late Oct. | ||
* Kickoff discussion with Hardware consulting vendor Kaizen Dynamics to support creation early sensor prototypes. | |||
*Project Goals: | *Project Goals: | ||
** Evidence from the experiments to show the consumer needs. (consumer service) | ** Evidence from the experiments to show the consumer needs. (consumer service) |