Confirmed users
172
edits
| Line 31: | Line 31: | ||
| Chad, Karen, Rob | | Chad, Karen, Rob | ||
| Johnathan Nightingale, Mark Mayo and Andreas Gal elevated FxAcct + Sync to first priority for their respective teams and the 29 iteration as the deadline. | | Johnathan Nightingale, Mark Mayo and Andreas Gal elevated FxAcct + Sync to first priority for their respective teams and the 29 iteration as the deadline. | ||
| ✔ | | align="center" | ✔ | ||
|- style="background-color: #777; color: white;" | |- style="background-color: #777; color: white;" | ||
| colspan="7" | Friday, January 3rd - 18 Work Days Remaining | | colspan="7" | Friday, January 3rd - 18 Work Days Remaining | ||
| Line 43: | Line 43: | ||
| Chad, Karen, Rob | | Chad, Karen, Rob | ||
| Chad indicated that he's ready to flag day desktop. Karen researching Android users response to a flag day. | | Chad indicated that he's ready to flag day desktop. Karen researching Android users response to a flag day. | ||
| On Track | | align="center" | On Track | ||
|- style="background-color: #777; color: white;" | |- style="background-color: #777; color: white;" | ||
| colspan="7" | Friday, January 10th - 13 Work Days Remaining | | colspan="7" | Friday, January 10th - 13 Work Days Remaining | ||