| 1. STATUS | |||||
| Status Item | On Track | Caution | Crisis | N/A | Comment |
| OVERALL STATUS | X | ||||
| Schedule | X | ||||
| Scope | X | ||||
| Budget | X | ||||
Schedule & Budget
| 2. SCHEDULE | |||
| Start Date | Completion Date | ||
| Original | Current | Original | Current |
| Jan 30 2012 | Jan 30 2012 | April 11, 2011 | N/A |
| 3. BUDGET | |||
| Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
| N/A | N/A | N/A | N/A |
Recent Accomplishments
| 4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
| 5. UPCOMING TASKS | ||||
| Task | Owner | Due Date | Bugzilla | Comments |
| Launch Release 1 | Pierros | 2012-02-28 | Complete | |
| Approve Milestone Dates Of Release 2 | Teams | 2012-03-02 | - | In Progress |
| Scope & Plan + Milestone Dates Of Release 2 | Pierros/BS | 2012-02-20 | - | Complete |
Major Issues
| 6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
| Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
| - | - | - | - | - | - | ||
Project Milestones
| 7. PROJECT MILESTONES | |||||||
| Issue | Owner | Target Completion Date |
Revised Completion Date |
Acutal Completion Date |
Bugzilla | Status | |
| ReMo Team | |||||||
| Release 1 Ready To Test | GL | 2/3 | 2/7 | 2/9 | Complete | ||
| Release 1 Live | GL | 2/28 | |||||
| Release 2 Ready To Test | GL | 3/9 | |||||
| Release 2 Live | GL | 4/2 | |||||
| Release 3 Live | GL | TBD | |||||
| WebDev | |||||||
| Release 1 Review | JW & PM | 2/3 - 2/6 | 2/9 - 2/10 | 2/10 | Complete | ||
| Release 2 Review | JW & PM | 3/12 - 3/14 | |||||
| Privacy/Legal | |||||||
| Release 1 Review | SM | 2/8 - 2/24 | 722528 | In progress | |||
| Release 2 Review | N/A (Confirm) | ||||||
| QA | |||||||
| Release 1 Review | SD | 2/8 - 2/15 | 722518 | In Progress | |||
| Release 2 Review | SD | 3/12 - 3/19 | |||||
| Security | |||||||
| Release 1 Review | YB | 2/15 - 2/24 | 722521 | In Progress | |||
| Release 2 Review | YB | 3/19 - 3/23 | |||||
| IT | |||||||
| Setup Dev | JM | 1/30 | 718584 | Complete | |||
| Setup Staging | JM | 2/14 | 2/13 | 719262 | Complete | ||
| Setup Production | JM | 2/24 | 2/9 | 720473 | Complete | ||