Iteration #12 Status Report

Overall Project Performance

  • From Iterations #1 - #12:
    • Total Project Story Points: 966
    • Story Points Completed: 704
    • Story Points Remaining to Completion: 262
    • Team Velocity: 65 Per Iteration
    • Iterations Remaining to Completion: 4
    • Forecasted Date to Completion of Development: October 11, 2013
    • Total Stories Closed: 232
    • Percentage of Work Completed: 73%

Metro Preview Release

The Metro Preview Release is the en-US feature complete preview planned to be available on the Aurora channel during the Aurora 26 cycle.

  • All feature stories, defects and changes required for the Metro Preview Release: View Backlog

  • At the conclusion of Iteration #12, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75,75,77,80, the Metro Team has a median velocity of 65 and there is a 90% likelihood that the actual velocity will fall between 33 and 75.

  • With a velocity performance of 65 the Metro Team can expect to complete between 132 and 300 more units of work with a median value of 262.

  • With a forecasted total of 262 points remaining development would be completed in 4 iterations on October 11, 2013 - Development Iteration #16.

  • The Metro Preview Release build is forecasted to "ride the trains" for Firefox 26
    • Iteration #13 completed on mozilla-central August 26th, 2013.
    • Iteration #14 completed on mozilla-central September 10th, 2013.
    • Merge to Aurora 26 on September 16, 2013 during Iteration #15.
    • Iterations #15 and #16 will be completed on mozilla-aurora, concluding all Preview Release work.
    • A Windows Aurora Firefox build will be publicized as the Metro Preview Release.
    • Iteration #17, still on Aurora, will be used to clean up any remaining carry-over and polish work.
    • Merge to Beta at the conclusion of Iteration #17 on October 28, 2013, making Metro Firefox available to our Beta audience.
    • Iterations #18 and #19 will be available if needed for responding to any critical Beta feedback issues that surface.
    • Push to Release on December 10 with Firefox 26 at the conclusion of Iteration #20.

Iteration #12 Performance

  • Performance Highlights
    • Team completed 80 story points across 30 features which resulted in an increased average team velocity of 65 story points per iteration.
    • Average team velocity rate increased 3% from the previous iteration.
    • Point closure increased 6% from the previous iteration.

  • Quality Highlights
    • The quality performance from the regression testing across Iterations #1 - #11 is as follows:
      • 94% pass rate - a 2% increase from the previous iteration.
      • 6% fail rate - a 25% reduction from the previous iteration.
      • 100% test coverage.

Bugzilla query error

Array ( [type] => error [message] => http-bad-status [params] => Array ( [0] => 406 [1] => Not Acceptable ) ) 1

Iteration Performance History

Iteration #1: View Backlog

  • Story Points Completed = 30
  • Stories Completed = 5
  • Team Velocity: 30 Per Iteration

Iteration #2: View Backlog

  • Story Points Completed = 32
  • Stories Completed = 6
  • Team Velocity: 32 Per Iteration

Iteration #3: View Backlog

  • Story Points Completed = 33
  • Stories Completed = 10
  • Team Velocity: 32 Per Iteration

Iteration #4: View Backlog

  • Story Points Completed = 63
  • Stories Completed = 14
  • Team Velocity: 40 Per Iteration

Iteration #5: View Backlog

  • Story Points Completed = 75
  • Stories Completed = 25
  • Team Velocity: 47 Per Iteration

Iteration #6: View Backlog

  • Points Completed: 74
  • Stories Completed: 20
  • Team Velocity: 51 Per Iteration

Iteration #7: View Backlog

  • Points Completed: 68
  • Stories Completed: 23
  • Team Velocity: 54 Per Iteration

Iteration #8: View Backlog

  • Points Completed: 46
  • Stories Completed: 21
  • Team Velocity: 53 Per Iteration

Iteration #9: View Backlog

  • Points Completed: 51
  • Stories Completed: 15
  • Team Velocity: 51 Per Iteration

Iteration #10: View Backlog

  • Points Completed: 75
  • Stories Completed: 30
  • Team Velocity: 57 Per Iteration

Iteration #11: View Backlog

  • Points Completed: 77
  • Stories Completed: 34
  • Team Velocity: 63 Per Iteration

Iteration #12: View Backlog

  • Points Completed: 80
  • Stories Completed: 30
  • Team Velocity: 65 Per Iteration

Upcoming Iteration