Build/Infrastructure Team Radar, August 2006

High Priority

  • Bouncer2 test installation deployment on Khan (morgamic/clouser, ETA: 8/15)
  • 1.8/Trunk test coverage on new testing farm (rhelmer, ETA: 8/10)
  • Firefox 2.0b2 release work (preed, week of 8/7, for 2 weeks)
  • Mac UB Tinderbox bringups (coop)

Medium Priority

  • Round 2 of VM migrations (coordination: preed; work: IT)
  • Reference platform work; define VC 6 ref platform (preed) (ETA: 8/25)
  • XULRunner + FFx trunk build machine bringup (bug 315452, ETA: 8/15)

Ongoing

  • Open source AUS2 with patcher2 tools (bug 346926)
  • Clean up FTP mirrors
  • Tbox 2 testing/investigations (rhelmer)

Completed!