IT/Production Acceptance/QMO2
< IT | Production Acceptance
Jump to navigation
Jump to search
Start of project
Name each of the following:
- Project sponsor: Jay Patel
- Main IT contact: Oremj
- Main WebDev contact: Morgamic
- Main QA contact: Stephend
- Main third party contact (if developed externally): TBD
- Final application owner/maintainer: Jay Patel
Overall goal of the project
- Improve Mozilla QA team and community collaboration; centralize all QA related documentation and make it easy to keep updated; organize QA related activities and encourage more participation from the Mozilla community (betatesters, bug triage, data analysis, etc)
Any pre-requisites needed (technology, server capacity, staffing, monitoring, response time, etc):
- Access to SVN needed for Jay and any potential developers working on project
- Will https://bugzilla.mozilla.org/show_bug.cgi?id=431872 give me access to QMO2?
- Staging server required
Initial timeline
- Goal is to have new QMO site live in "beta" form by July 2008.
- Rough schedule:
- Staging server of Drupal 5 (5/12)
- [P1] Drupal views and module integration (5/19)
- Content creation and site configuration (Ongoing)
- [P1] Theme implementation (6/6)
- Live templates at http://people.mozilla.com/~jpatel/qmo/templates/
- Download files at http://people.mozilla.com/~jpatel/qmo/templates/templates.zip
- [P2] Custom module development and projects/events improvements (TBD)
- RFP has more info: http://people.mozilla.com/~jpatel/qmo/QMO_Drupal_Dev.pdf
External dependencies
- Might outsource:
- Drupal theme development
- Custom module/feature development
Dev environment specs
- Same as SFX work with Raincity
Staging Signoff
In order to get an app into staging, the following should be completed:
- Code committed to Mozilla source control and tagged
- Initial architecture review by IT and WebDev
- Site must be password protected
- Review timeline to go live
- Review any production requirements so IT can order any new hardware needed
Production Signoff/Launch
- Final WebDev signoff
- Final IT signoff
- Final QA signoff
- Operations documents filled for support & any training complete
- Monitors in place