Current QMO Redesign Project
** [[QA/Community/QMO_Design/Design Doc | Design Document (to pass on to design team)]]
** [[QA/Community/QMO_Design/Airbag | QMO Redesign with Airbag Industries]]
** [http://people.mozilla.com/~jpatel/qmo/templates/ Final QMO design templates from Airbag]* Phase 2: Drupal Development (April June - July August 2008)** Bidding process underwayin April/May, decided to go with [http://www.advomatic.com/ Advomatic]. will be deciding on firm by week of May 4** Delay in development process due to lengthy contact negotiation with Advomatic (5/13 - 6/20)** Development schedule*** Drupal 6 config (July 1 - 7)*** Theme development (July 1 - 15+?)*** Module development (July 15 - August 15+?)*** Alpha testing and bug fixing (August 15 - August 31)*** QMO beta release (September) 