Overall Project Health
Last week: Green
This week: Green
Exec Summary
- Formal kick off of project occurred, RACI established
- Use case gathering in process (creates exit criteria)
- Risk retirement in process
Risks/Issues
| Description of Risks/Issues | State | Owner | Plan to Resolve/Mitigation | Target Date |
|---|---|---|---|---|
| Get sign off on proposal | In process | Georg | sign offs required from TestPilot (Will Clouser), Ilana, RobFromBRC, John Dorlus, | ASAP |
| Notify Org post signoff | TBD | Thomas/Georg | Notify FX-Team, UITour stakholders, Jared, Mike Connoly | TBD |
| Item | Item | Item | Item | Item |
| Item | Item | Item | Item | Item |
| Item | Item | Item | Item | Item |
Accomplished for Last Period
- Kick off meeting
- RACI established
- investigations/Action items were generated
Planned for Next Period
- Rebecca, Ilana and Rob Miller to define use cases
- Define exit criteria
- Follow up meeting between Georg and Rob Miller
- Follow up with AS/Tim Spurway (Thomas, Georg and Roberto)
- BDS - The strawman: why don’t we just use Google Analytics?
Proposed development stages and status
| Stage | State | description | Target Date |
|---|---|---|---|
| Proposal creation | Done | accepted | August 1, 2016 |
| Kick off | Done | RACI + develpoment stages | August 14, 2016 |
| Development to allow test pilot to begin using and submitting | TBD | ingestion, storage, make available for analysis | TBD |
| QA Validation | TBD | Test to validate UITelemtry | TBD |
| Processing | TBD | TBD | TBD |
| Tooling | TBD | TBD | TBD |