User:Mconnor/Current/ServicesEngPlanTemplate
Overview
link to feature page, explain generically what we're building and how
Key People
| Technical Lead: | Some Guy |
| Additional Developers: | |
| Project Manager: | Someone Else |
| Product Manager: | So many people |
| UX: | ETOO_MANY_CHEFS |
Work Items
Main Team
Top-level tracking bug: bug 1234560
Do a Thing
| Assigned to: | Some Guy |
| Bug: | 1234567 |
| Assumes/Depends On: | depends on Other Thing |
| Working Estimate: | 8 days
Best case: 5 days |
Other Thing
| Assigned to: | Some Other Guy |
| Bug: | 1234562 |
| Assumes/Depends On: | Some Guy defines reqs on time |
| Working Estimate: | 25 days
Best case: 12 days |
External Dependencies
Deploy Thing to Stage Infra
| Assigned to: | Some Ops Guy |
| Bug: | 1234564 |
| Assumes/Depends On: | Things are done |
| Working Estimate: | 6.5 days
Best case: 3 days |
Deploy Thing to Beta Infra
| Assigned to: | Some Ops Guy |
| Bug: | 1234563 |
| Assumes/Depends On: | Stage Infra deploy done |
| Working Estimate: | 11 days
Best case: 5 days |
Timeline
Expected Completion
Here's where we do some logical construction. because we have a serial set of dependencies here, we have straight math, but where things can be parallelized we can do different things
Working Estimate: 50 days == 2.5 months. Assuming today is June 15th, the earliest likely launch date is September 6th.
Milestones
obviously we'll add in more data as we can
M1 (Engineering Work)
Working Estimate: 33 days == seven weeks
Target Completion (ready for infra) is Aug 5th
M2 (Deployments)
Working Estimate: 17 days == four weeks
Target Completion, starting from Sept 2nd