Tasks

Application

P1

Status Description Link
Microsummary service doesn't guarantee cache loaded before updating bug 336837
Pending review Microsummaries should be removed when they cease to exist bug 338295
Pending review Automatically update installed microsummary generators bug 341341
Need the caller's browser for infobar approach. C++ impl. needed? Microsummary generator installation gives no indication that it succeeded bug 341818
Needs bug 102699 Use DOMParser to parse HTML bug 361449
Complete Check HTTP status code to determine auth (and other) failures bug 370242
Complete Generated titles (microsummaries) are not used in tree and menu places views bug 373500
Microsummary service test suite bug 387207
Import generatedTitles and set staticTitles appropriately bug 389579

P2

Status Description Link
Property of bookmarks? UI for removing microsummary generators bug 341336
Privacy concerns? Set the referrer header when downloading a generator linked by a page bug 342591
At Risk Enable script execution in Microsummaries bug 361026
Allow getMicrosummaries() to take an optional document argument bug 387206
Add FTP support to MicrosummaryResource bug 391316

Future

Status Description Link
Needs spec Support rich text microsummaries bug 341347
Microformat or meta tag? Enable pages to specify microsummaries within the pages themselves bug 358105

Web

SVN Repository

P1

Status Description Link
Complete Design database schema schema.sql
Design/implement API
Design/implement user-facing features
Implement administration tools

Extension

SVN Repository

Microsummary Manager @ AMO

P1

Status Description Link
Utilize web API

P2

Status Description Link
Extend support for author meta-data
Implement generator updates for 1.8

Schedule

M7

  • All blockers in

M7+1 week

  • Update feature in
  • Definitive answer on new UI/mockups

M7+2 weeks

  • First-pass implementation of web app complete
  • Majority of P1s complete

M7+3 weeks

  • P1s complete
  • Majority of P2s complete

August 20

  • End of project under SoC
  • Web app fully completed, tested and deployed to a temporary home along with companion extension

M7+4 weeks - M8+

  • Polish and regression fixes as needed
  • Find more permanent home for web app