Firefox3/Schedule: Difference between revisions
< Firefox3
Jump to navigation
Jump to search
m (deleted extra space) |
|||
| Line 31: | Line 31: | ||
| [http://www.mozilla.org/projects/firefox/3.0a4/releasenotes/ Gran Paradiso alpha 4 release notes] | | [http://www.mozilla.org/projects/firefox/3.0a4/releasenotes/ Gran Paradiso alpha 4 release notes] | ||
|- valign="top" | |- valign="top" | ||
| Alpha 5 | | Alpha 5 || June 6, 2007 | ||
| | |||
June 6, 2007 | |||
| [http://www.mozilla.org/projects/firefox/3.0a5/releasenotes/ Gran Paradiso alpha 5 release notes] | | [http://www.mozilla.org/projects/firefox/3.0a5/releasenotes/ Gran Paradiso alpha 5 release notes] | ||
|- valign="top" | |- valign="top" | ||
Revision as of 18:43, 11 June 2007
Please do not edit these pages without permission of the Gran Paradiso steering group. Your feedback and comments are welcomed on the discussion page.
Mozilla Developer's Calendar
The Mozilla Developer's Calendar holds the most up to date schedule for the development milestones and planned release dates of Mozilla products:
- subscribe to the ICS file (use Mozilla Sunbird, Apple iCal, or Google Calendar)
- add the calendar to your Google Calendar account.
- view the calendar as a webpage.
Gecko 1.9 / Firefox3 Milestone Schedule
This is draft milestone schedule for Gecko 1.9 and the Gran Paradiso release. We are currently in early-planning stages for Firefox 3, so these dates should not be considered fixed, but rather as a reflection of our current estimates. E.g. these are *draft* dates.
- Proposal for L10N cut-off dates
| Release | Date | Description |
| Alpha 1 | December 2006 | Developer Preview ("Dogfood") Gran Paradiso alpha 1 release notes |
| Alpha 2 | 8 Feb 2007 | Gecko 1.9a2 Release Notes, Gran Paradiso alpha 2 release notes |
| Alpha 3 | 23 March 2007 | Gran Paradiso alpha 3 release notes |
| Alpha 4 | 27 April 2007 | Gran Paradiso alpha 4 release notes |
| Alpha 5 | June 6, 2007 | Gran Paradiso alpha 5 release notes |
| Alpha 6 |
|
|
| Beta 1 |
|
Feature Frozen, including UI. All strings complete avail for l10n for planned features. Still allowances for string changes as a result of feedback from Beta1.
|
| Beta 2 | September 2007 | First l10n builds. All strings frozen two weeks prior to beta 2 release. Really frozen. String changes past this will cause overall schedule slippage. |
| Additional Betas and RCs based on need |