** Provide more details on project critical path;showing the user stories to deliver for the various project milestones. | ** Provide more details on project critical path;showing the user stories to deliver for the various project milestones. | ||
** Provide detail project cost analysis; fixed vs variable, scale market cost for min and max, data cost for AWS usage | ** Provide detail project cost analysis; fixed vs variable, scale market cost for min and max, data cost for AWS usage | ||
* Kicked off Branding review on project requirements to support program launch | * Kicked off Branding review on project requirements to support program launch | ||
** Checkin in 2 wks with proposed branding framework | |||
* Kicked off User study #1 for user interviews in Taipei for late Oct. | * Kicked off User study #1 for user interviews in Taipei for late Oct. | ||
** Preparing user interaction walkthru and interviewee questions along with 3D prototype | ** Preparing user interaction walkthru and interviewee questions along with 3D prototype. | ||
* Kicked off discussion with Hardware consulting vendor | * Kicked off discussion with Hardware consulting vendor to support creation of early sensor prototypes by end of Dec 2016. | ||
** Review this week on Hardware components list and Hardware development Schedule for Dec 2016 | ** Review this week on Hardware components list and Hardware development Schedule for Dec 2016 | ||
|- | |- | ||
| Line 72: | Line 74: | ||
*Completed revisions in Vaani server code | *Completed revisions in Vaani server code | ||
*Continued work to engage a company to produce a video to describe the overall purpose and functionality of Abigail to get consumer feedback. | *Continued work to engage a company to produce a video to describe the overall purpose and functionality of Abigail to get consumer feedback. | ||
* | *Working on value propositions | ||
*Leveraging detailed research study with busy families (about 20 in Vancouver and local Bay Area) conducted by Rina and Mihaela, where questions were around concepts that were a focus of Cue, Vaani, and Smart Kitchen past projects. They’re working on synthesizing this data. | |||
*Working on best ways to collect data from study participants - i.e. forming the right questions | |||
'''Work Week Goals''' | '''Work Week Goals''' | ||
*Complete end-to-end integration for one reminder use-case, say “Remind me to pickup Sasha at 4pm today” | *Complete end-to-end integration for one reminder use-case, say “Remind me to pickup Sasha at 4pm today” | ||
| Line 78: | Line 82: | ||
*Finalize details of User Study Plan, including what we want to learn and how | *Finalize details of User Study Plan, including what we want to learn and how | ||
'''Schedule''' | '''Schedule''' | ||
*Prototype development: month of October (includes Oct 17th Work Week in SF) | |||
*Assembly of devices: week of October 31 | |||
*Testing in homes: November 7 - 18 | |||
*Data synthesis from pilot and video/landing page studies: November 21 - 29 | |||
*Gate 1 pitch: November 30 | |||
|- | |- | ||
| [[Connected_Devices/Projects/Project_Magnet|Project Magnet]] | | [[Connected_Devices/Projects/Project_Magnet|Project Magnet]] | ||
| Line 121: | Line 125: | ||
| | | | ||
'''Home Monitoring System''' | '''Home Monitoring System''' | ||
[[File:Project_homeweb_wordmark.png|500px]] | [[File:Project_homeweb_wordmark.png|500px]] | ||
| Line 147: | Line 152: | ||
*Use case refinement has narrowed the scope of a first iteration prototype that will be proposed in Gate 0 pitch | *Use case refinement has narrowed the scope of a first iteration prototype that will be proposed in Gate 0 pitch | ||
*Refining the Gate 0 pitch and will send it out for feedback in the coming week | *Refining the Gate 0 pitch and will send it out for feedback in the coming week | ||
*Gate 1 pitch: November 30 | |||
'''Engineering''' | '''Engineering''' | ||
*Development of a game board simulator and also a physical board with an LED base | *Development of a game board simulator and also a physical board with an LED base | ||
| Line 165: | Line 171: | ||
! style="background:#00EC00;" | On Target | ! style="background:#00EC00;" | On Target | ||
| | | | ||
* | '''Engineering''' | ||
* | *Work on image matching is progressing well. Might work well enough to not have to worry about separating out background during image acquisition | ||
*Testing alternatives for mic/speaker, including Wolfson card, Wilson card that uses I2S expansion bus on rpi, as well as USB option. Goal is to make a quick decision so that prototype can be assembled in time for the study. | |||
* Team is looking for an additional engineer to help on this project | |||
'''User Study with Prototype''' | |||
*Testing hypotheses around technical feasibility, that study participants will trust it, not the testing of specific form factors. | |||
*Current thinking is that team members will accompany participants on shopping outings and possibly assist in taking photos of the items being purchased, as the focus of the study is on how well image matching works, not on how easy it is for the participants to take the photos. | |||
'''Schedule''' | |||
*Complete development of prototype: October | |||
*Assemble prototypes: Oct 31 - Nov 4 | |||
*Prototype pilot: Nov 7 - 18 | |||
*Data synthesis from pilot and video/landing page studies: November 21 - 29 | |||
*Gate 1 pitch: November 30 | |||
|- | |- | ||
| PocketID | | PocketID | ||
| Line 175: | Line 192: | ||
* No update this week, as the team has been working on projects with higher priority. | * No update this week, as the team has been working on projects with higher priority. | ||
|- | |- | ||
<!--- | |||
| 3D Printing | | 3D Printing | ||
| Thomas | | Thomas | ||
| Line 183: | Line 201: | ||
* Bulleted list item | * Bulleted list item | ||
|- | |- | ||
---> | |||
| [[Connected_Devices/Participation|Participation Update]] | | [[Connected_Devices/Participation|Participation Update]] | ||
| Michael/Brian | | Michael/Brian | ||
| Line 188: | Line 207: | ||
! style="background:#00EC00;" | On Target | ! style="background:#00EC00;" | On Target | ||
| | | | ||
* | * No new update | ||
|- | |- | ||
| Market Developments Update | | Market Developments Update | ||
Latest revision as of 17:42, 13 October 2016
<< Connected Devices Weekly Updates Home
| Program | Passed Gate | Status | Notes | |
|---|---|---|---|---|
| Project Sensor Web | Cindy/Jean | Gate 1 | On Target |
|
| Project_Haiku (taking in Project Smart Display) | Liz/Joe/Mahe | Gate 0 | On Target |
|
| Platform and Tools | Sandip/Nicole | N/A | On Target |
Breaking down near/medium term Platform goals
Weekly Notes:
|
| Voice Platform - Deep Speech | Sandip/Nicole | N/A | On Target |
|
| Abigail | Preeti/Julie | Gate 0 | On Target |
Prototype Development and Testing
Work Week Goals
Schedule
|
| Project Magnet | David/Maria | Gate 0 | On Target |
Vision
Problem Statement
Product
|
| Project HomeWeb | Ben/Mahe | Gate 0 | On Target |
Home Monitoring System Gate 0 approved, pending allocation of resources (otherwise known as "people"). Wiki page: https://wiki.mozilla.org/Connected_Devices/Projects/HomeWeb Next steps:
|
| GameON! | Candice/Julie | Pre Gate 0 | On Target |
Product Definition
Engineering
|
| Lighthouse | Preeti/Julie | Gate 0 | On Target |
Engineering
User Study with Prototype
Schedule
|
| PocketID | Francisco | Pre Gate 0 | On Target |
|
| Participation Update | Michael/Brian | -- | On Target |
|
| Market Developments Update | Irina |
| ||