Connected Devices Weekly Update/2016-10-27: Difference between revisions
Jump to navigation
Jump to search
(re-sized photo) |
No edit summary |
||
| Line 12: | Line 12: | ||
! style="background:#00EC00;" | On Target | ! style="background:#00EC00;" | On Target | ||
| | | | ||
* | * PIB Checkin completed Fri, Oct 21 to provide follow up action items from Oct 4 Gate1 review: | ||
* | ** Provide details project plan, Architecture diagram and AWS data hosting costs. Refer to [https://docs.google.com/presentation/d/1MUDBv-WKynWvc8EQQHkGheJgih8qPDuD8ZFcIrq2fLk/edit?ts=57ebf743#slide=id.g18560693f3_0_94 Gate 1 Pitch Check-in] deck for more details. | ||
* Kicked off User study #1 for user interviews in Taipei to start Oct 25 to 28. | |||
** This study will cover UI/ID and installation, unboxing experience, user interaction of setup process and value proposition. | |||
** Milestone Delivered: Confirmation on Oct 25 a list of key components list and detail Hardware Development Schedule with task and ownership to meet our early prototype deadline for Dec 2016. | |||
* Upcoming Tasks: | |||
** Share results from User Study #1 in Taipei. | |||
** Kick off pricing sensitivity study in Taipei in mid to late Nov. | |||
** SensorWeb Branding Checkin meeting with Branding team early Nov to review proposed branding framework. | |||
|- | |- | ||
| [[Connected_Devices/Projects/Project_Haiku|Project_Haiku (taking in Project Smart Display)]] | | [[Connected_Devices/Projects/Project_Haiku|Project_Haiku (taking in Project Smart Display)]] | ||
Revision as of 16:54, 27 October 2016
<< Connected Devices Weekly Updates Home
| Program | Passed Gate | Status | Notes | |
|---|---|---|---|---|
| Project Sensor Web | Cindy/Jean | Gate 1 | On Target |
|
| Project_Haiku (taking in Project Smart Display) | Liz/Joe/Mahe | Gate 0 | On Target |
|
| Platform and Tools | Sandip/Nicole/Mahe | N/A | On Target |
|
| Voice Platform - Deep Speech | Sandip/Nicole | N/A | On Target |
|
| Abigail | Preeti/Julie | Gate 0 | On Target |
Concept Validation
Work Week Results
Abigail Study with Prototypes
Schedule
|
| Project Magnet | David/Maria | Gate 0 | On Target |
Target Audience (MVP)
Stories
|
| HomeWeb | Ben/Mahe | Gate 0 | On Target |
Technical Feasibility Study
Landing Page Experiment
Early draft of landing page (partial): |
| GameON! | Candice/Julie | Pre Gate 0 | On Target |
Work Week Progress
Gate 0 Pitch
Prototype testing
|
| Lighthouse | Preeti/Julie | Gate 0 | On Target |
Engineering The Lighthouse code now enables a user to do the following:
User Study with Prototype
Form Factor Study
Schedule
|
| 3D Printing | Thomas | Pre Gate 0 | On Target |
|
| Participation Update | Michael/Brian [READ ONLY] | -- | On Target |
|
| Market Developments Update | Irina |
| ||
| Other Announcements / Questions | -- | -- | ||