Line 164: Line 164:


===== rebron =====
===== rebron =====
Two week goals (end of week 2):
* Support documentation, audit (see what we have on .org and .com) and plan for what we need for beta 2 and final release.
* Web site production hand-off to silver orange and global teams. 
* Update SpreadThunderbird with analytics module, events module and printed materials.


===== sipaq =====
===== sipaq =====

Revision as of 16:34, 30 December 2008

last meeting | index | next week »

Thunderbird Meeting Details

Agenda

Calls For Help

Action Items

New

Open

  • dmose - Draw up straw man schedule for shipping one month after Firefox.
  • dmose - Suggest to drivers about a new flag for potential post-TB3 blockers.

Closed

Thunderbird 3 Beta 2

  • For reference, Gecko 1.9.1b3: Jan 13 Code Freeze, Jan 15 QA, Jan 26 Release according to their plan.
  • clarkbw is release driver
  • gozer is build engineer
  • Proposed: Slushy string freeze from: Monday 2nd February 23:59 PST
  • Proposed: Firm string freeze and slushy Code freeze from: Thursday 5th February 23:59 PST

Thunderbird 3

QA Updates

  • topcrashes
    • bug 422907 nsMsgLocalMailFolder::GetTrashFolder (rootFolder is null)
    • bug 470804 NS_GetInnermostURI (CAPS?) (TB2) (no "owner")
    • bug 470808 nsProxyEventObject::CallMethod (imap)
    • bug 470835 nsMsgLocalMailFolder::AddMessage (should be fixed in 12-23 nightly)

Roundtable

Status Updates

davida
dmose
nth10sd
  • Now back full steam post-Christmas & through the new year.
  • Usual occasional bug triage.
  • Working on first automated TB litmus test 5426.
  • Got some TB patches into MozMill.
    • getMail3PaneController() should work perfectly.
    • getAddrbkController() should also work (almost) perfectly.
    • Now there's only a non-working new/getMsgComposeController() left..
      • (Taken out since there's a simple keypress workaround)
jcranmer
Standard8
  • Reviews
  • Password Manager
    • Almost complete patch now available on bug 433316
    • Need to sort out "password protect cache" - have some ideas, hope to solidify this week.
    • Also still need one sr in ldap before it can land bug 419595
  • Mozmill in Leak & Bloat
    • Did some work to simplify running mozmill with TB and highlight the parts that are still preventing us from running the tests automatically, raised bug 471510 to cover the details
  • Misc
    • bug 468108 Pointed the l10n dashboard to the right repository (mozilla-1.9.1) for l10n comparisons etc

Two week goals (End of week 2):

  • Complete Password Manager migration
    • See above, almost complete
  • Complete moving Leak and Bloat to Mozmill
  • Lead Address Book discussions
    • Delayed due to Christmas
  • Investigate fixing LDAP Issues with threads and shutdown.
    • Delayed due to Christmas
  • Look at Performance tests
    • Delayed due to Christmas

Two week goals (Start of week 1):

  • Complete Password Manager migration
  • Complete moving Leak and Bloat to Mozmill (if Mozmill issues are resolved)
  • Investigate if there is a simpler way to switch fully to toolkit autocomplete without doing too much work.
  • Look at Performance tests
    • Get some rough ideas of what & how.
    • See if we can get a Ts structure in place (or something else)
      • This would be useful for jemalloc and assessing implementing a packages-static file for unix.
asuth
bienvenu

Two week goals (end of week 2):

  • Turn autoconfig branch into a reviewable patch for trunk
    • Deferred rest of work until I've finished the folder archiving work
    • Got autoconfig working again on the branch, made all the strings localizable, and added code to prevent creation of duplicate accounts.
  • Finish folder compaction changes and unit tests.
    • patch up for review
  • Reduce review queue backlog
    • Review queue in reasonable shape.

Two week goals (week 2)

  • Finish folder archiving work. bug 451995
    • several dependent bugs fixed or awaiting review
    • rest of work will probably have to wait until next week

Two week goals (week 1)

  • Try to knock off some beta 2 blockers between the holiday festivities
emre
  • Two week goals
    • Finalizing activity manager and activity manager integration of core components.
    • Implementing a two level auto-sync model for TB-Idle cases.
gozer
  • Build
    • Rewrote the unittest buildbot master to be branch-capable
      • Moving builders over to it as we speak
    • Mac OS X now using Dwarf (crash symbols issues seem resolved too)
  • Web
    • SpreadThunderbird Google Analytics live.
    • Got a fully working bouncer installation, need to think about production setup
  • Personnal
    • On vacation: Jan 9th - Jan 16th (on call)
clarkbw
wsmwk
beckley
Penelope
KaiRo
rkent
rebron
sipaq
mkmelin