Mobile/Projects/Kinderfox/Status/22-Jul-2015
Jump to navigation
Jump to search
Status Report for Fennec - Kinderfox - for the period ending 24/07/2015
Overall Project Health
This Week | Last Week |
---|---|
N/A |
Exec Summary/Hot Topics
- A fixed backlog has been created for the V1 release, and sizing estimates applied.
- V1 scope has been defined to produce a minimum viable product. If any features are determined to not be possible for the 42 release, this means the V1 as a whole is not viable for 42.
- Approximately 40% of the scoped work is assigned and in progress, while 57% is not yet started.
Risks & Issues
Description of Risk/Issue | State | Owner | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|
Lorem ipsum dolor sit amet consetetur sadipscing elitr sed diam nonumy eirmod tempor invidunt ut labore et dolore magna aliquyam erat sed diam voluptua | Open | Joey | At vero eos et accusam et justo duo dolores et ea rebum Stet clita kasd gubergren no sea takimata sanctus est Lorem ipsum dolor sit amet | February 30th |
Accomplished for the Last Period
- Landed 1125316
- V1 Scope defined and backlog sizing completed
Planned for Last Period but Not Accomplished
Planned for the Upcoming Period
Status Details
Summary of Engineering Work
- Done - 3%
- In Review - 12%
- Assigned - 28%
- Available - 57%
- Example1.jpg
Example Chart 1 - Add Name Here
- Example2.jpg
Example Chart 2 - Add Name Here