User:Mconnor/Current/ServicesEngPlanTemplate

From MozillaWiki
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Overview

link to feature page, explain generically what we're building and how

Key People

Technical Lead: Some Guy
Additional Developers:
Project Manager: Someone Else
Product Manager: So many people
UX: ETOO_MANY_CHEFS

Work Items

Main Team

Top-level tracking bug: bug 1234560

Do a Thing

Assigned to: Some Guy
Bug: 1234567
Assumes/Depends On: depends on Other Thing
Working Estimate: 8 days

Best case: 5 days
Worst case: 15 days
Most Likely: 7 days

Other Thing

Assigned to: Some Other Guy
Bug: 1234562
Assumes/Depends On: Some Guy defines reqs on time
Working Estimate: 25 days

Best case: 12 days
Worst case: 50 days
Most Likely: 22 days

External Dependencies

Deploy Thing to Stage Infra

Assigned to: Some Ops Guy
Bug: 1234564
Assumes/Depends On: Things are done
Working Estimate: 6.5 days

Best case: 3 days
Worst case: 15 days
Most Likely: 5 days

Deploy Thing to Beta Infra

Assigned to: Some Ops Guy
Bug: 1234563
Assumes/Depends On: Stage Infra deploy done
Working Estimate: 11 days

Best case: 5 days
Worst case: 20 days
Most Likely: 10 days

Timeline

Expected Completion

Here's where we do some logical construction. because we have a serial set of dependencies here, we have straight math, but where things can be parallelized we can do different things

Working Estimate: 50 days == 2.5 months. Assuming today is June 15th, the earliest likely launch date is September 6th.

Milestones

obviously we'll add in more data as we can

M1 (Engineering Work)

Working Estimate: 33 days == seven weeks

Target Completion (ready for infra) is Aug 5th

M2 (Deployments)

Working Estimate: 17 days == four weeks

Target Completion, starting from Sept 2nd