General info

  • Members
    • Jose Manuel Cantera
    • Sergi Mansilla
    • Francisco Jordano
    • Adrian de la Rosa (guest star)
  • Meetings:
    • Daily happening on IRC currently on channel #fxos-comms at 11:00 CET
    • Subteam sprint planning: last day before the global sprint planning, IRC on channel #fxos-contacts at 10:00 CET
  • Holidays:
    • Jose Cantera: 15th August - 10th September
    • Francisco Jordano: 4th September - 7th September

List of bugs

Contacts issues for this sprint

Bugzilla query error

Array ( [type] => error [message] => http-bad-status [params] => Array ( [0] => 406 [1] => Not Acceptable ) ) 1


Sprint planning

Daily meetings

Day 3: 3rd September 2014

Adrian de la Rosa

  • Working on:
    • bug 1056268 — [Contacts] when importing contacts search function is missing functionality
    • bug 1060101 — [Settings][Facebook] Removing a Facebook account from Contacts will not finish if Facebook was set up during the FTU / FTE

Francisco Jordano

  • Working on:
    • bug 1061068 — [Contacts] ICE missing from top of the list when toggling the 'Order by last name'
    • bug 1061413 — [Contacts] Favorites on top of ICE if ICE set first, and Favorites set later
    • bug 1061421 — [Contacts] Delete all contacts which were set to ICE, 'ICE contacts' list is empty but the whole ICE
    • Today mostly working on reviews

Sergi Mansilla

  • Working on:
    • bug 1061504 — Add/Delete icon animation to fields in contact form
    • bug 1062189 — Images in the contacts list are shifted to the right, overlapping letter shortcuts

Day 4: 4th September 2014

Adrian de la Rosa

  • Worked on:
    • bug 1056647 — [Contacts] Refactor the FB sync schedule and remove it from the app critical path
    • bug 1056268 — [Contacts] when importing contacts search function is missing functionality
  • Working on:
    • bug 1060101 — [Settings][Facebook] Removing a Facebook account from Contacts will not finish if Facebook was set up during the FTU / FTE

Francisco Jordano

  • On PTO

Sergi Mansilla

  • Worked on:
    • bug 1061504 — Add/Delete icon animation to fields in contact form
    • bug 1062189 — Images in the contacts list are shifted to the right, overlapping letter shortcuts
  • Working on:
    • Reviews
    • bug 1061941 [Settings][Facebook] Removing a Facebook account from Contacts will not finish if Facebook was set up during the FTU / FTE


Day 8: 10th September 2014

Adrian de la Rosa

    • bug 1060101 — [Settings][Facebook] Removing a Facebook account from Contacts will not finish if Facebook was set up during the FTU / FTE

Francisco Jordano

    • bug 1061421 — [Contacts] Delete all contacts which were set to ICE, 'ICE contacts' list is empty but the whole ICE

Sergi Mansilla

    • bug 1061504 — Add/Delete icon animation to fields in contact form
    • bug 1062189 — Images in the contacts list are shifted to the right, overlapping letter shortcuts
    • Reviews

Jose Manuel Cantera

    • bug 1062595 - No confirm window pops up to inform users that deleted numbers are removed from an ICE contact.

Demos

Retrospective

Actions taken from last sprint

Things that went well

  • Good start with estimations, we should continue estimating and tweaking and learning from it.
  • Choosing Trello was a good decision

Things that went not that well

  • We didn't learn well our tools (eg. Trello) on time for the sprint
  • More thorough testing to avoid edge cases on features to bite us back
  • Improve feedback for the demo (screenshots, etc.)
  • We are a team that has less time than other to purely code (bc of different reasons, mostly related to developers being part of partner companies and the team lead needing time for management).

Actions for this sprint

  • Reduce hours/day of coding per developer to 4.
  • Express every task in multiples of 3 hours.
  • Every member in the team needs to learn how to use Trello.
  • Properl configure burn down chart.