** Smoketest Greenness - Latest length of time that we haven't had smoketest regressions needs to be greater than five days
** Smoketest Greenness - Latest length of time that we haven't had smoketest regressions needs to be greater than five days
** MTBF Test Run lasts for 30+ hours
** MTBF Test Run lasts for 30+ hours
* Perfomance team sign-off to ensure we have met the FC ready criteria
* Perfomance criteria: AppStartuptime < 1 second
 
'''Notes :'''
'''Notes :'''
* [TBD] Hard string freeze happens in two weeks as we enter the the FC phase giving the localization team four weeks to localize the strings and prepare for a testrun at FC. FC will typically mark the launch of the initial l10n test run.