canmove, Confirmed users, Bureaucrats and Sysops emeriti
1,922
edits
No edit summary |
No edit summary |
||
| Line 43: | Line 43: | ||
|'''OPEN - Monitor''' | |'''OPEN - Monitor''' | ||
|Jenn/Eng Mgt | |Jenn/Eng Mgt | ||
| align="left"|The team is smaller by 1.5 full-time, plus 1 intern, compared to V1.0 resourcing. Scope and resource allocation | | align="left"|The team is smaller by 1.5 full-time, plus 1 intern, compared to V1.0 resourcing. Scope and resource allocation will be monitored closely throughout the project. | ||
|Ongoing | |Ongoing | ||
| Line 50: | Line 50: | ||
|'''OPEN - Monitor''' | |'''OPEN - Monitor''' | ||
|Jenn/Eng Mgt | |Jenn/Eng Mgt | ||
| align="left"| | | align="left"| Development timelines required to deliver must-have features are very tight. No scope creep can be permitted, and progress to be monitored closely. Any 'nice-to'have' features that did not meet string freeze will not be considered for the release. | ||
|Ongoing | |Ongoing | ||
<!--Copy and paste the section below to add additional rows and maintain table formatting --> | <!--Copy and paste the section below to add additional rows and maintain table formatting --> | ||
| Line 71: | Line 71: | ||
== Accomplished for the Last Period == | == Accomplished for the Last Period == | ||
<!--Both deliverables; code and actions; and decisions. Remove example text below--> | <!--Both deliverables; code and actions; and decisions. Remove example text below--> | ||
* V1 | * V1.1 builds #4 & #5 released to internal aurora and external test flight | ||
* Team continues working toward V1.1 features | |||
** Private Browsing - feature complete | |||
* Team continues working toward V1.1 features | ** Bookmark Sync - landed | ||
* | ** FxA Sign-Up - in review | ||
** Adjust - landed | |||
** Clear Private Data Granularity - feature complete | |||
** Tour updates - in progress | |||
== Planned for Last Period but Not Accomplished == | == Planned for Last Period but Not Accomplished == | ||
<!--Both deliverables; code and actions; and decisions. Remove example text below--> | <!--Both deliverables; code and actions; and decisions. Remove example text below--> | ||
<!--Items that DID NOT meet their target date, which fell in the last reporting period--> | <!--Items that DID NOT meet their target date, which fell in the last reporting period--> | ||
* | * N/A | ||
== Planned for the Upcoming Period == | == Planned for the Upcoming Period == | ||
<!--Both deliverables; code and actions; and decisions. Remove example text below--> | <!--Both deliverables; code and actions; and decisions. Remove example text below--> | ||
<!--All items due over the next reporting period. Including those items missed last period if the new target date falls in the next period. i.e., you will have some repeated items from the previous section--> | <!--All items due over the next reporting period. Including those items missed last period if the new target date falls in the next period. i.e., you will have some repeated items from the previous section--> | ||
* V1.1 Build # | * EN Copy for locked fields - 10/08 | ||
* | * V1.1 Build #6 - 10/15 | ||
* Blog Post read for final approval - 10/16 | |||
* Dev/L10N Freeze - 10/19 | |||
== Status Details <!--Optional Section If Needed--> == | == Status Details <!--Optional Section If Needed--> == | ||