| Line 14: | Line 14: | ||
| 0.4 | | 0.4 | ||
| planning stage | | planning stage | ||
| Boriss contacting Aza/Alex on 4/8, | | Boriss contacting Aza/Alex on 4/8, and estimating full design delivery by 5/1. Pinged on 4/9. No estimate until get some UX info. | ||
|- | |- | ||
| 104 | | 104 | ||
| Simple storage | | Simple storage | ||
| Drew | | Drew | ||
| 0.4 | | 0.4 | ||
| blocked | | blocked | ||
| | | Blocked by {{bug|553020}} (which is at-risk for 0.3) | ||
|- | |- | ||
| 105 | | 105 | ||
| Line 28: | Line 28: | ||
| 0.4 | | 0.4 | ||
| planning stage | | planning stage | ||
| | | Blocked by {{bug|553020}} (which is at-risk for 0.3), and on the EM's support for reboot-less extension installs. Estimate 2 weeks for implementation. | ||
|- | |- | ||
| 108 | | 108 | ||
| Line 34: | Line 34: | ||
| Felipe | | Felipe | ||
| 0.4 | | 0.4 | ||
| | | planning stage | ||
| Felipe is looking at | | Felipe is looking at use-cases and technical requirements. Estimating 2 weeks for implementation. | ||
|- | |- | ||
| 109 | | 109 | ||
| Line 41: | Line 41: | ||
| Zpao | | Zpao | ||
| 0.4 | | 0.4 | ||
| | | planning stage | ||
| | | Some implementation already done. Paul estimates 2 weeks for implementation. | ||
|- | |- | ||
| 112 | | 112 | ||
| Line 49: | Line 49: | ||
| 0.3 | | 0.3 | ||
| on-track | | on-track | ||
| | | | ||
|- | |- | ||
| 114 | | 114 | ||
| Line 56: | Line 56: | ||
| 0.4 | | 0.4 | ||
| in-progress | | in-progress | ||
| Core work done by ddahl, but needs | | Core work done by ddahl, but needs API review for Jetpack API consistency. Marco is out on vacation, but said some API and code work still needs to happen, but nothing major. Still targeting 0.4 for now. | ||
|- | |- | ||
| 116 | | 116 | ||
| Line 63: | Line 63: | ||
| 0.4 | | 0.4 | ||
| not started | | not started | ||
| | | Paul talked with Myk about the spec, estimates 2 weeks for implementation. | ||
|} | |} | ||