| Line 25: | Line 25: | ||
* Prior to the release date, and in coordination with a QA engineer, a developer with the appropriate permissions pushes the release to staging. | * Prior to the release date, and in coordination with a QA engineer, a developer with the appropriate permissions pushes the release to staging. | ||
* QA engineers run automated and ad-hoc tests against staging, seeking clarification where necessary and marking bugs with the appropriate status. | * QA engineers run automated and ad-hoc tests against staging, seeking clarification where necessary and marking bugs with the appropriate status. | ||
* On the release date | * On the release date: | ||
** An engineer with production push authority tags VERIFIED code with the Bugzilla release number | |||
** That code is pushed to production | |||