Program Management/Firefox/2013-Q2-Goals: Difference between revisions

Line 26: Line 26:
*** 12 feature stories shifted to a P4 priority level.
*** 12 feature stories shifted to a P4 priority level.
* '''{{done|}}''' Develop a Pessimistic, Optimistic and Expected Release Scenario.  The initial figures will be presented following the conclusion of Iteration #6 and will be updated at the conclusion of each upcoming iteration.
* '''{{done|}}''' Develop a Pessimistic, Optimistic and Expected Release Scenario.  The initial figures will be presented following the conclusion of Iteration #6 and will be updated at the conclusion of each upcoming iteration.
** At the end of Iteration #6, the Metro project had enough performance data to establish the three release scenarios:
** At the end of Iteration #6, the three release scenarios were as follows:
*** Pessimistic Release Scenario - March 20, 2014:  The average velocity figure of the '''worst 3 iterations is 32'''.  If the team drops to this velocity figure, then development would be completed no earlier than '''19 iterations on March 20, 2014'''.   
*** Pessimistic Release Scenario - The average velocity figure of the '''worst 3 iterations is 32'''.  If the team drops to this velocity figure, then development would be completed no earlier than '''19 iterations on March 20, 2014'''.   
*** Optimistic Release Scenario - October 02, 2013:  The average velocity figure of the '''best 3 iterations is 71'''.  If this velocity figure can be achieved and maintained, then development would be completed no later than '''9 iterations on October 02, 2013'''.   
*** Optimistic Release Scenario - The average velocity figure of the '''best 3 iterations is 71'''.  If this velocity figure can be achieved and maintained, then development would be completed no later than '''9 iterations on October 02, 2013'''.   
*** Expected Release Scenario - November 19, 2013:  The average velocity figure from '''all the previous iterations is 51'''.  If this velocity figure can be maintained, then development would be completed in '''12 iterations on November 19, 2013'''.  
*** Expected Release Scenario - The average velocity figure from '''all the previous iterations is 51'''.  If this velocity figure can be maintained, then development would be completed in '''12 iterations on November 19, 2013'''.
** At the end of Iteration #7, the three release scenarios were as follows:
*** Pessimistic Release Scenario - The average velocity figure of the '''worst 3 iterations is 32'''. If the team drops to this velocity figure, then development would be completed no earlier than '''18 iterations on March 20, 2014'''. 
*** Optimistic Release Scenario The average velocity figure of the '''best 3 iterations is 72'''.  If this velocity figure can be achieved and maintained, then development would be completed no later than '''8 iterations on October 02, 2013'''. 
*** Expected Release Scenario - The average velocity figure from '''all the previous iterations is 54'''.  If this velocity figure can be maintained, then development would be completed in '''11 iterations on November 19, 2013'''.  
* Maintain 'triage' backlog at no more than 10 items at the conclusion of Q2.
* Maintain 'triage' backlog at no more than 10 items at the conclusion of Q2.
* Maintain 'planning' backlog at no more than 10 items at the conclusion of Q2.
* Maintain 'planning' backlog at no more than 10 items at the conclusion of Q2.