| Line 25: | Line 25: | ||
=== Schedule === | === Schedule === | ||
* code freeze is scheduled for Wednesday, October 17th | * code freeze is scheduled for Wednesday, October 17th | ||
* we pulled back to threat level orange on Thursday due to the number of remaining blockers | * we pulled back to threat level orange on Thursday due to the number of remaining blockers | ||
* [http://tinyurl.com/3d8y8w M9 Blockers]: 81 (7 are [http://tinyurl.com/34fwoj unassigned]) | |||
** some of those bugs can be moved out to post M9, mconnor to re-triage | |||
** some of those would not block an alpha, so we either need to move code freeze or declare M9 to be another alpha and shift some blockers to M10 | |||
** at our current fix rate, we'd need 2 more weeks to contain all the bugs | |||
** impact of this slip would mean only 1 beta in 2007, as our dates would shift beta 2 to be too far into December | |||
** worried that slipping/extending will just see us "grow to fit" the deadline | |||
** '''action item:''' mconnor and damons to review M9 blocker lists and report back at Gecko meeting tomorrow with estimates of when we could ship a decent Beta 1. | |||
=== Work in progress === | === Work in progress === | ||