The following proposed schedule assumes no re-spin. | The following proposed schedule assumes no re-spin. | ||
* Tree closure: January 22 | * Tree closure / l10n freeze: January 22 | ||
* Code freeze: January | * Code freeze: January 29 | ||
* Build starts: | * Build starts: February 4 | ||
* QA/Testing starts: | * QA/Testing starts: February 4/5 | ||
* Final release: 1.5 weeks later (or so) | * Final release: 1.5 weeks later (or so) |