Websites/Snippets/Impressions/Weekly-Status-Reports/2012-02-03
< Websites | Snippets | Impressions
Summary
| DOC VERSION: 1.0 | STATUS REPORT AS OF: Feb 03, 2012 |
| AUTHOR: Benjamin Sternthal |
| TPM: Benjamin Sternthal |
| PROJECT SPONSOR: Laura Forrest |
| PROJECT WIKI: Websites/Snippets/Impressions |
Status
| 1. STATUS | |||||
| Status Item | On Track | Caution | Crisis | N/A | Comment |
| OVERALL STATUS | X | ||||
| Schedule | X | ||||
| Scope | X | ||||
| Budget | X | ||||
Schedule & Budget
| 2. SCHEDULE | |||
| Start Date | Completion Date | ||
| Original | Current | Original | Current |
| Jan 20 | Jan 20 | March 7 | N/A |
| 3. BUDGET | |||
| Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
| N/A | N/A | N/A | N/A |
Recent Accomplishments
| 4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
| 5. UPCOMING TASKS | ||||
| Task | Owner | Due Date | Bugzilla | Comments |
| Create Mana Item For Zeus | cshields / bsternthal | 02/06/2012 | N/A | |
| Workout/confirm milestone schedule | bs/team | 02/06/2012 | N/A | |
| Collection Testing On Staging? | bsternthal | 02/11/2012 | N/A | |
Major Issues
| 6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
| Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
| IT | High | 01/27/2012 | 698815 | Resolved | |||
Project Milestones
| 7. PROJECT MILESTONES | |||||||
| Issue | Owner | Target Completion Date |
Revised Completion Date |
Acutal Completion Date |
Bugzilla | Status | |
| WebDev | |||||||
| Interface & JS | MK | 2/27 - 3/1 | 690881 | ||||
| Privacy | |||||||
| Review Collection Data | TBD | 2/17 | 723589 | ||||
| Security | |||||||
| Security Review | YB | 3/1 - 3/5 | 723596 | ||||
| QA | |||||||
| Selenium Tests | SD | 2/21 - 2/24 | 724114 | ||||
| QA Review | SD | 3/1 - 3/5 | 723600 | ||||
| IT | |||||||
| Confirm & Document Zeus Solution | CS | 2/17 | 698815 | ||||
| Metrics | |||||||
| Stage Dashboard | AP | 4/15 | |||||