* Offer out to Marco
* Offer out to Marco
* More on 2013 staffing
* More on 2013 staffing
* How are you using the artifacts (project plan, lifecycle, etc.) from the PM offsite?
* Next PM offsite? First week of Feb?


==Dietrich==
==Dietrich==
* Daily driving of remaining user stories bugs.
* Daily stand-ups with Qualcomm and Mister Treese, and driving of those bugs.
* Working on detailing the 1.0 customization options for use by OEMs and carriers.
* Trying to get ahead of incoming OEM hardware changes.


==Erin==
==Erin==
;Mobile Roadmap
* ARMVv6 Testing: shepherding of Mob4Hire continues; sourcing HW
* Managing risk around product announcements, readability (we should be closing the deal on font licensing this week
* Marketplace: Packaged Apps triage and scoping. Banner shipped in FX17 Beta unplanned and we are negotiating removal for Beta 3
* Sync2.0: Need alignment around identity pieces, there is a meeting among dev managers today
* Fx Android roadmap review for 2013 tomorrow
* MWC Planning and coordination
** In Progress: Weekly status. This needs to happen!
;Metro
** Long poles: meeting with Milan on thurs, sync/shared profiles reside on the same dependencies as Fx Android
** Cleaning up timeline with Martin to align with users stories on Wed


==Lawrence==
==Lawrence==
* Platform technical roadmap
** Continue to get feedback, refine and expand audience.
* B2G
** Platform triage has ramped up. Booked for 1h daily. Some days taking 2+ hours for triage related work.
* Performance
** Outstanding Telemetry enabled-by-default blockers: update download pages, update press FAQ, land code change, final sign-off from Jishnu
* Mobile Web Compat
** Getting closer on updates for UA detection frameworks/products
** Deep dive site investigation in {{bug|811421}} wrapped up, review this Thurs
** Reviewing list of potential sites for B2G UA whitelist


==Martin==
==Martin==
* Drove QA review of User Stories for Metro.
* Worked on Projection Model.
* Worked on plan for this weeks iteration meeting.
* Reporting on various projects.


==Michael==
==Michael==
* Integrate Marketing timelines with current FFOS TCL and ZTE timelines
* Propose FFOS overall program review for all teams: Engineering, Marketplace, etc.
* Daily meetings with QC


==Sheila==
==Sheila==
* Hiring plan for 2013
** Trying to fill remaining req's for 2012
** Likely won't get everything for 2013
* Helping with Engineering goals
* Social API
** Planning v1.5
** Working on multi-provider support
* Firefox Health Report
** Lots of pieces in play, slow to get closure.
* Stability
** Handing off most tracking to Kairo, still helping the team with some intiatives