* From Iterations #1 - #2:
** Total Points Completed:  '''62'''
** Total Stories Closed:  '''11'''
** Team Point Velocity:  '''31 per iteration'''
** Average Stories Closed:  '''5.5 per iteration'''
** Average Point Closure Rate:  '''29% per iteration'''
** Scope Change (Defects and Changes):  '''17 points over 7 stories'''
* [https://bugzilla.mozilla.org/show_bug.cgi?id=838081 Story Backlog:]  '''26''' stories ready for upcoming iterations.
* [https://bugzilla.mozilla.org/show_bug.cgi?id=839143 Legacy Backlog:]  '''6''' stories remaining for QA testing.
* [https://bugzilla.mozilla.org/show_bug.cgi?id=839336 On Hold Backlog:]  '''4''' stories remaining for Product Manager clarification before being moved into Story Backlog.
* [https://bugzilla.mozilla.org/show_bug.cgi?id=841214 Triage Backlog:]  '''43''' items for Product Manager to review before being converted to defects, changes or work.
* [https://bugzilla.mozilla.org/show_bug.cgi?id=841997 Planning Backlog:]  '''33''' stories for Team to review, relate to work items and assign point values.
{| border="1" cellpadding="2"
|- valign="top"
|width="10%"|'''Iteration #1'''
|width="20%"|
* '''Iteration Points'''
** Committed = '''102'''
** Completed = '''30'''
** Closure Rate = '''29.4%'''
* '''Scope Change'''
** New Defects Generated = '''0'''
** New Changes Generated = '''3 points over 1 story'''
|- style="vertical-align:top;"
|'''Iteration #2'''
|
* '''Iteration Points'''
** Committed = '''110'''
** Completed = '''32'''
** Closure Rate = '''29.1%'''
* '''Scope Change'''
** New Defects Generated = '''4 points over 2 stories'''
** New Changes Generated = '''10 points over 4 stories'''
|}
====Iteration #3 - In Progress====
* Iteration Backlog:  [https://bugzilla.mozilla.org/show_bug.cgi?id=839392 Firefox Metro Iteration #3:  February 26, 2013 - March 11, 2013]
* Team Committment:  '''72''' points over '''12 stories'''
* Progress To Date:
** '''22''' points completed over '''7''' stories.
** '''50''' points over '''5''' stories remain to complete iteration.
====Iteration #4 - Upcoming====
* Iteration Backlog:  [https://bugzilla.mozilla.org/show_bug.cgi?id=842108 Firefox Metro Iteration #4:  March 14, 2013 - March 27, 2013]


==Sheila==