QA/TCM/Releases/.1: Difference between revisions
Jump to navigation
Jump to search
| Line 93: | Line 93: | ||
| carljm | | carljm | ||
| | | | ||
# | # will push latest changes | ||
# debugging platform changes | |||
# hook up templates test cycle, test run, environments, run test page | |||
| | | | ||
# 2/1 | # 2/1 | ||
# 2/3 | |||
# 2/3 | |||
|- | |- | ||
| Dev | | Dev | ||
| emeyer | | emeyer | ||
| | | | ||
# | # should have something to show on thursday | ||
| | | | ||
# | # 2/4 | ||
|- | |- | ||
| QA | | QA | ||
| camd | | camd | ||
| | | | ||
# | # | ||
| | | | ||
# | # | ||
|- | |- | ||
| etc. | | etc. | ||
| Line 118: | Line 121: | ||
# send e-mail for feedback after feature-complete | # send e-mail for feedback after feature-complete | ||
| | | | ||
# 2/ | # 2/3 | ||
|} | |} | ||
Revision as of 16:45, 1 February 2011
Goals
- Allow "testers" to run tests
- Allow "testers" to create tests
Designs & Requirements
- to Add
- Must Have Bug Fixes
- Should Have Bug Fixes
- Nice to Have Bug Fixes
Team
- Dev: carljm, emeyer
- QA: camd
- etc.: aakashd
Milestones
| Status | Step | Owner | ETA | Actual |
|---|---|---|---|---|
| [DONE] | Define Designs & Requirements | aakashd | 12/9 | 12/9 |
| [ON TRACK] | Code Freeze | carljm/emeyer | 1/27 | |
| [ON TRACK] | QA complete | camd | 1/31 | |
| [ON TRACK] | Go Live | aakashd/carljm | 2/1 |
Status
Latest Work Done
| Piece | Person | Description |
|---|---|---|
| Dev | carljm |
|
| Dev | emeyer |
|
| QA | camd |
|
| etc. | aakashd |
|
Next Steps
| Piece | Person | Description | Tentatively Due |
|---|---|---|---|
| Dev | carljm |
|
|
| Dev | emeyer |
|
|
| QA | camd |
|
|
| etc. | aakashd |
|
|
QA
Bugs can be filed using this form
A list of open bugs can be found here