User:Mconnor/Current/ServicesEngPlanTemplate: Difference between revisions
No edit summary |
|||
| Line 1: | Line 1: | ||
= Overview = | |||
'''link to feature page, explain generically what we're building and how''' | '''link to feature page, explain generically what we're building and how''' | ||
= Key People = | |||
{{ProjectTeam | {{ProjectTeam | ||
| Line 13: | Line 13: | ||
}} | }} | ||
== Main Team | = Work Items = | ||
== Main Team == | |||
Top-level tracking bug: {{bug|1234560}} | Top-level tracking bug: {{bug|1234560}} | ||
| Line 39: | Line 39: | ||
}} | }} | ||
== External | == External Dependencies == | ||
{{WorkItem | {{WorkItem | ||
| Line 63: | Line 63: | ||
}} | }} | ||
= Timeline = | |||
== Expected Completion == | |||
'''Here's where we do some logical construction. because we have a serial set of dependencies here, we have straight math, but where things can be parallelized we can do different things''' | '''Here's where we do some logical construction. because we have a serial set of dependencies here, we have straight math, but where things can be parallelized we can do different things''' | ||
| Line 71: | Line 71: | ||
Working Estimate: 50 days == 2.5 months. Assuming today is June 15th, the earliest likely launch date is September 6th. | Working Estimate: 50 days == 2.5 months. Assuming today is June 15th, the earliest likely launch date is September 6th. | ||
== Milestones == | |||
''' obviously we'll add in more data as we can ''' | ''' obviously we'll add in more data as we can ''' | ||
=== M1 (Engineering Work) === | |||
Working Estimate: 33 days == seven weeks | Working Estimate: 33 days == seven weeks | ||
| Line 81: | Line 81: | ||
Target Completion (ready for infra) is Aug 5th | Target Completion (ready for infra) is Aug 5th | ||
=== M2 (Deployments) === | |||
Working Estimate: 17 days == four weeks | Working Estimate: 17 days == four weeks | ||
Target Completion, starting from Sept 2nd | Target Completion, starting from Sept 2nd | ||
Latest revision as of 21:25, 7 June 2011
Overview
link to feature page, explain generically what we're building and how
Key People
| Technical Lead: | Some Guy |
| Additional Developers: | |
| Project Manager: | Someone Else |
| Product Manager: | So many people |
| UX: | ETOO_MANY_CHEFS |
Work Items
Main Team
Top-level tracking bug: bug 1234560
Do a Thing
| Assigned to: | Some Guy |
| Bug: | 1234567 |
| Assumes/Depends On: | depends on Other Thing |
| Working Estimate: | 8 days
Best case: 5 days |
Other Thing
| Assigned to: | Some Other Guy |
| Bug: | 1234562 |
| Assumes/Depends On: | Some Guy defines reqs on time |
| Working Estimate: | 25 days
Best case: 12 days |
External Dependencies
Deploy Thing to Stage Infra
| Assigned to: | Some Ops Guy |
| Bug: | 1234564 |
| Assumes/Depends On: | Things are done |
| Working Estimate: | 6.5 days
Best case: 3 days |
Deploy Thing to Beta Infra
| Assigned to: | Some Ops Guy |
| Bug: | 1234563 |
| Assumes/Depends On: | Stage Infra deploy done |
| Working Estimate: | 11 days
Best case: 5 days |
Timeline
Expected Completion
Here's where we do some logical construction. because we have a serial set of dependencies here, we have straight math, but where things can be parallelized we can do different things
Working Estimate: 50 days == 2.5 months. Assuming today is June 15th, the earliest likely launch date is September 6th.
Milestones
obviously we'll add in more data as we can
M1 (Engineering Work)
Working Estimate: 33 days == seven weeks
Target Completion (ready for infra) is Aug 5th
M2 (Deployments)
Working Estimate: 17 days == four weeks
Target Completion, starting from Sept 2nd