User:Mconnor/Current/ServicesEngPlanTemplate: Difference between revisions

From MozillaWiki
Jump to navigation Jump to search
No edit summary
 
Line 1: Line 1:
== Overview ==
= Overview =


'''link to feature page, explain generically what we're building and how'''
'''link to feature page, explain generically what we're building and how'''


== Key People ==
= Key People =


{{ProjectTeam
{{ProjectTeam
Line 13: Line 13:
}}
}}


== Main Team Work Items ==
= Work Items =
 
== Main Team ==
Top-level tracking bug: {{bug|1234560}}
Top-level tracking bug: {{bug|1234560}}


Line 39: Line 39:
}}
}}


== External Work Items ==
== External Dependencies ==


{{WorkItem
{{WorkItem
Line 63: Line 63:
}}
}}


== Timeline ==
= Timeline =


=== Expected Completion ===
== Expected Completion ==


'''Here's where we do some logical construction.  because we have a serial set of dependencies here, we have straight math, but where things can be parallelized we can do different things'''
'''Here's where we do some logical construction.  because we have a serial set of dependencies here, we have straight math, but where things can be parallelized we can do different things'''
Line 71: Line 71:
Working Estimate: 50 days == 2.5 months.  Assuming today is June 15th, the earliest likely launch date is September 6th.
Working Estimate: 50 days == 2.5 months.  Assuming today is June 15th, the earliest likely launch date is September 6th.


=== Milestones ===
== Milestones ==


''' obviously we'll add in more data as we can '''
''' obviously we'll add in more data as we can '''


==== M1 (Engineering Work) ====
=== M1 (Engineering Work) ===


Working Estimate: 33 days == seven weeks
Working Estimate: 33 days == seven weeks
Line 81: Line 81:
Target Completion (ready for infra) is Aug 5th
Target Completion (ready for infra) is Aug 5th


==== M2 (Deployments) ====
=== M2 (Deployments) ===


Working Estimate: 17 days == four weeks
Working Estimate: 17 days == four weeks


Target Completion, starting from Sept 2nd
Target Completion, starting from Sept 2nd

Latest revision as of 21:25, 7 June 2011

Overview

link to feature page, explain generically what we're building and how

Key People

Technical Lead: Some Guy
Additional Developers:
Project Manager: Someone Else
Product Manager: So many people
UX: ETOO_MANY_CHEFS

Work Items

Main Team

Top-level tracking bug: bug 1234560

Do a Thing

Assigned to: Some Guy
Bug: 1234567
Assumes/Depends On: depends on Other Thing
Working Estimate: 8 days

Best case: 5 days
Worst case: 15 days
Most Likely: 7 days

Other Thing

Assigned to: Some Other Guy
Bug: 1234562
Assumes/Depends On: Some Guy defines reqs on time
Working Estimate: 25 days

Best case: 12 days
Worst case: 50 days
Most Likely: 22 days

External Dependencies

Deploy Thing to Stage Infra

Assigned to: Some Ops Guy
Bug: 1234564
Assumes/Depends On: Things are done
Working Estimate: 6.5 days

Best case: 3 days
Worst case: 15 days
Most Likely: 5 days

Deploy Thing to Beta Infra

Assigned to: Some Ops Guy
Bug: 1234563
Assumes/Depends On: Stage Infra deploy done
Working Estimate: 11 days

Best case: 5 days
Worst case: 20 days
Most Likely: 10 days

Timeline

Expected Completion

Here's where we do some logical construction. because we have a serial set of dependencies here, we have straight math, but where things can be parallelized we can do different things

Working Estimate: 50 days == 2.5 months. Assuming today is June 15th, the earliest likely launch date is September 6th.

Milestones

obviously we'll add in more data as we can

M1 (Engineering Work)

Working Estimate: 33 days == seven weeks

Target Completion (ready for infra) is Aug 5th

M2 (Deployments)

Working Estimate: 17 days == four weeks

Target Completion, starting from Sept 2nd