| ==1.4 Schedule== | | ==1.4 Schedule== |
| * Milestones Schedule
| |
| #Sprint 1 – feature dev :: 2/3/14 – 2/14/14
| |
| #Sprint 2 – feature dev :: 2/17/14 – 2/28/14
| |
| #Sprint 3 – feature dev :: 3/3/14 – 3/14/14
| |
| #Sprint 4 – Planning (1.5) :: 3/17/14 – 3/28/14
| |
| ##Sprint 4 - 1.4 stabilization begins
| |
| #Sprint 5 – stabilization :: 4/1/14 – 4/11/14
| |
| #Sprint 6 – stabilization :: 4/15/14 – 4/25/14
| |
| #Internal feature complete :: 3/14/2014
| |
| #Hard string Freeze :: 3/28/2014
| |
| #QA end to end test run :: 3/17/14 - 3/28/14 (sprint 4)
| |
| #Localization bug fixes complete :: 03/31/2014 – 04/21/2014
| |
| #Localization testrun :: 4/1/14 - 4/11/14 (sprint 5)
| |
| #RTP - Release to Partner :: 4/25/2014
| |
| #Feature list walk through 1.4 :: 3/17/2014
| |
| #Convergence branch creation :: 3/17/2014
| |
| #Convergence done :: 4/25/2014
| |
| #QC CS :: Currently 5/15 (will negotiate to 06/20/2014)
| |
| #Regular blocker triage with RM :: 3/17/14 onwards
| |
| #No more approvals on gaia flags :: 3/24/2014
| |
| #End to end regression 2 :: 4/15-14 - 4/25/14 (sprint 6)
| |
| #End to end regression 3 :: post RTP -- on 1.4 branch
| |
| #Company Bug Bash :: week of 4/15/14 (sprint 6)
| |
| #Recommended IOT test start/ Customization testing complete :: 4/25/14 onwards
| |
| #Recommended final IOT testing :: based on partner
| |
| #TA :: 11/20/2014
| |
|
| |
| <table border=1> | | <table border=1> |
| <caption>1.4 MILESTONES</caption> | | <caption>1.4 MILESTONES</caption> |