Firefox OS/OneDotFourTracking
From MozillaWiki
1.4 ROADMAP
https://wiki.mozilla.org/B2G/Roadmap#Key_Focus_1.4_Features
1.4 Schedule
MILESTONE | SCHEDULE |
---|---|
SPRINT 1 DEV | 2/3/14 – 2/14/14 |
SPRINT 2 DEV | 2/17/14 – 2/28/14 |
SPRINT 3 DEV | 3/3/14 – 3/14/14 |
SPRINT 4 PLANNING | 3/17/14 – 3/28/14 |
SPRINT 5 STABILIZATION | 4/1/14 – 4/11/14 |
SPRINT 6 STABILIZATION | 4/15/14 – 4/25/14 |
INTERNAL FEATURE COMPLETE | 3/14/2014 |
FEATURE LIST WALK THROUGH | 3/17/2014 |
CONVERGENCE BRANCH CREATION | 3/17/2014 |
JOINT TRIAGE | 3/17/2014 onwards |
DEADLINE FOR GAIA APPROVALS | 3/24/2014 |
QA END to END TEST RUN | 3/17/2014 - 3/28/2014 |
HARD STRING FREEZE | 3/28/2014 |
REGRESSION 1 | 4/15/2014 - 4/25/2014 |
1.4 BUG BASH | week of 4/15/2014 |
RTP - RELEASE TO PARTNER | 4/25/2014 |
RECOMMENDED IOT START/ CUSTOMIZATION COMPLETE | 4/25/2014 |
CONVERGENCE DONE | 4/25/2014 |
QC: CS | 5/15/2014 |
REGRESSION 2 | POST RTP on 1.4 BRANCH |
TA | 11/20/2014 |