6-22-2010
What's been completed:
- Frederic
- All remaining bugs fixed
- Aakash
- Tested Feedback Extension and identified nits to change
- Verified warning notification on submission pages
What we aim to do next and when we expect to accomplish them:
- Frederic:
- GO LIVE!
- Aakash
- Create blog post/promotions as necessary
6-21-2010
What's been completed:
- Frederic
- Pretty much all bugs fixed
- Filed bug 573468 to go live
- Aakash
- Done with Privacy Policy stuff
- verified fixes
What we aim to do next and when we expect to accomplish them:
- Frederic:
- fix remaining bugs
- Try out Lee Tom's next background image if he gets it in time
- Aakash
- Test out Jono's fix
- Verify warning notification on submission pages
6-20-2010
What's been completed:
- Frederic
- Fixed a bunch of bugs over the weekend
- Aakash
- talking to legal about implementation of privacy policy text on submission pages
- verified fixes
- promoted out input to a wider audience and got some testers (go kbrosnan!)
What we aim to do next and when we expect to accomplish them:
- Frederic:
- fix remaining P1-P3's
- file bug to go live Tuesday night PST
- Aakash
- hash out implementation with legal and give Fred a solution
- talk to Jono to comment out URL inclusion on extension side
6-16-2010
What's been completed:
- Frederic
- finished all P1/P2's except 1
- received horlander's icons
- Aakash
- finished 2nd set of mock-ups for mobile firefox
- verified p1 and p2 fixes
What we aim to do next and when we expect to accomplish them:
- Frederic:
- fix vendor directory issue for IT to get up on staging
- load testing
- fix remaining P1's and P3's
- Aakash
- test Input on staging
- promote out input to a wider audience (i.e. key stakeholders: qa, marketing, ux, fx-team)
6-15-2010
What's been completed:
- Frederic
- finished all P1's except 1
- replied to horlander
- Aakash
- followed-up with stephen horlander
- worked on implementation with mobile firefox
- filed a few more bugs
What we aim to do next and when we expect to accomplish them:
- Frederic:
- p2 bugs and remaining p1 bug
- Aakash
- test changes after p1 and p2 fixes are done
- look into load testing
6-14-2010
What's been completed:
- Frederic
- got hosed due to late issue with the weave team
- Aakash
- sent graphics via e-mail
- extension created by jono and we're testing that side
- all bugs triaged
What we aim to do next and when we expect to accomplish them:
- Frederic:
- p1 bugs
- reply back to horlander about smiley icon sizes on submission pages & sentiment box
- Aakash
- test changes after p1 fixes are done
- look into load testing
6-10-2010
What's been completed:
- Frederic
- completed beta page
- wrote unit tests
- did not file bug since app is changing quite a bit
- Aakash
- gave list of user agents
- got VPN access and tested/filed bugs
- created bugzilla component
- gave mock-up for download page
What we aim to do next and when we expect to accomplish them:
- Frederic
- fixing P1/P2's
- file a bug to staging when all P1/P2s are fixed
- Aakash
- follow up horlander
- lee tom for icons and graphics
- work on layout of search results
- file/triage bugs as needed
6-08-2010
What's been completed:
- Frederic:
- Search is working, pop-down for URLs, menu box options
- Aakash:
- Got Lee Tom to work on Dashboard and Thank You page graphics and Horlander to work on platform-specific icons
- Jono is going to incorporate button implementation with Feedback
- Metrics and TP will give info on riak implementation once its completed
What we aim to do next and when we expect to accomplish them:
- Frederic:
- create intermediary page to download beta (6/9)
- write unit test to make sure all cases are covered to send users to the download page
- file a bug on putting dashboard and submission pages to staging for input-stage.mozilla.com, input.stage.mozilla.com/happy input-stage.mozilla.com/sad (6/9)
- Aakash
- make a list of user agents 6/8
- get VPN access 6/8
- give text for download page 6/8
- get info on uservoice/survey api implementation with mktg on fx betas 6/10
6-01-2010
What's been completed:
- Fred:
- Working dashboard up (i.e. screenshot)
- swear word filter completed,
- Dashboard can be seen at http://fwenzel.khan.mozilla.org:8001/ (no search, urls are working, menuboxes for product/advanced options), admin panel (for deleting sentiment and hide terms)
- More screenshots: sad form, thank you page
What we aim to do next and when we expect to accomplish them:
- Fred (by Thursday 6/3):
- get search working
- pop-down for URLs when clicked ( go to page only when hyperlink clicked)
- implement in menu box options
- Aakash (by Thursday 6/3):
- get some designer love for happy/sad faces, dashboard header and follow-up buttons on thank you page
- start looking into client side
- getting info from metrics on implementation help for riak on rev 2
Additional Notes?
- Aakash: get set up with VPN for future demos
5-27-2010
Status Update:
- Fwenzel
- completed = forms (post positive and negative feedback), completed-ish user agent parser,
- questions = app that searches with riak?, interval on dashboard is? (1 day, 1 week, 1 month)
- aakashd
- getting info from metrics on implementation help for riak on rev 2
Next Steps:
- fwenzel = making django app/dashboard (late next week)
- aakashd = looking at list of swear words (mid-5/27)