Identity/WeeklyMeeting/2011-11-14
< Identity | WeeklyMeeting
Last Week's Actions
- roadmap needed
- post-mortem on security bug, plus script
- calendar of items needed by end of quarter and who owns what.
- QA calendar/wiki to plan Dev then Stage stability testing before Prod goes live
- tech documentation from engagement
Major Progress
Dev
- "keep me signed in" feature, required by apps team, implemented and in beta (sans 'allow persistent' flag - a 5 star issue)
- train-2011.11.03 into production
- train-2011.11.10 into beta WITH BLOCKERS (will not ship next week, but up for testing)
- dbwriter process split off - process split required for prod hardware to be complete this week
- "Native Client Facilitation Server" proposed - a way to accelerate prototyping browserid in native (mobile/desktop) apps
- Starting to rely less on JavascriptMVC and their templates, using EJS directly.
- Flattened out client code structure for easier discoverability.
- Have started on a module system to replace JavascriptMVC, using it initially as an experiment for the profile.
- Starting on profile model/initial form controller/tests.
Security & Privacy
Ops
- staging/loadtest environment hardware has landed and is mostly built
- seriously beefy fast hardware
- waiting on network ACLs, ETA monday
- should have browserid software running by EOD tuesday (stage-browserid.services.mozilla.com)
- start load tests as soon as we have the scripts to drive it
- prod scl2 hardware has also landed
- still waiting on new load balancers (not a blocker for testing)
- mysql replication/monitoring strategy fleshed out (doc coming)
- working with infra-sec on documentation, vuln scans, more reliable CEF logging, and RSBAC rollout
QA
- The 11/03/2011 Train made it successfully through Beta last week:
- Bug 699962 - QA and deploy BrowserID train-2011.11.03 to production
- QA is now working on our thirteenth train:
- Bug 701934 - QA and deploy BrowserID train-2011.11.10 to production
- QA still needs to get some help from Lloyd and Petef on the BrowserID install issues on our ID2 VM.
- What is the current status of the RPMs for deploying to ID2?
- QA is working on wiki to track OPs build-outs for Dev, Test/CI, Stage, and Production.
- Will post link as soon as it is ready
- QA needs to new the current status of all deployment environments - will catch up with OPs this week.
- QA is also actively doing inventory on QA devices to make sure we are covered for iOS5 on iPhone and iPad.