* Release schedule
** Code freeze (for blockers): Apr 30 (Delayed, new date: May 4)** Registration server code complete: Apr 30 (Done)** String Freeze: Apr 30 (Delayed, new date: May 4)
** H/W set up complete and configured: May 5
** Load testing done : May 13
***** still waiting on captcha-less account creation support in the weave client, see {{bug|561391}}
*** Marketing
 
Notes:
 
* Outage last week because of a doubled up host. Some of the checks didn't catch it (intermittent 503s are not triggering nagios checks).
* Are we reporting 503s properly in the client?
* We need better documentation on who is handling pages and what to do?
* '''AI:''' mrz will own updating the runbook for production.
* '''AI:''' mrz will own the metrics.
* uTest contract is signed and done. mevans is going to talk to them today.
* client is looking really good. beta4 should be out today.
* pretty close to being string frozen as well.
* Sync server is ready to go. RC1 is on stage.
* Registration is also pushed on stage.
* All the h/w is installed, we are still on track for being done tomorrow.
* QA needs a large profile (Tracy on jury duty next week).
* Load testing scripts needs time from mhanson.