Revision as of 12:37, 23 January 2017
General info
- Sprint 11 from January 23th to February 3rd (2017)
- Participants Development Sprint: Francisco, Wilson, Sam, Guillaume, Francis, Isabel and Maria
- Links of interest:
Sprint objectives
According to the planned engineering work, last sprint (Sprint 10) we worked hard on the React components, so we are in good shape to finish them at the end of the first week of Sprint 11. We finished the App Navigation and Deep linking tasks too that were scheduled to be done in Sprint 11 but at the same time, we couldn't move too far in the Backend part.
During this sprint 11, we are not going to have visuals yet, we need to do all the work that doesn't require UI (Visual work will not be started until Jan 30th) It will include:
- Finishing all the React Components (at the end of the next week, Jan 27th)
- and all the backend part including the libraries. We expected to be finished at the end of next week, but probably it will take until the end of sprint 11. Sam will start working on API, and documenting it
Apart of this:
- Wilson started to post some mock up concept and we will continue with that until we have the final UI.
- Francisco wants also to build the the Geolocation component, no the geofencing, to ensure the app has the the localization ready to distribute it to the rest of the components and probably later he will try to give a hand in the offline strategy and the client API as both things have to be built together.
Development tasks Planning
Tasks or Bugs committed for this sprint
| Task | Assigned | Status | Status Notes |
|---|---|---|---|
| Create a MediaPlayer element for iOS and Android supporting the Opus codec | Sam | Ongoing | |
| Document development process for services | Sam | Ongoing | |
| Render POI view with dummy data | Wilson | Ongoing | |
| Audio component | Not started | Not just the player that is being done in "Create a MediaPlayer element for iOS and Android supporting the Opus codec" task but the screen that looks like a phone call, etc. | |
| Create cron to kick off nightly builds | Sam | Not started | |
| First testing round | Isabel | Not started | |
| Fav component | Not started | ||
| Share component | Not started | ||
| Carousel component | Francisco | Not started | |
| Create database "model" objects with a view to reuse in a library on the client | Not started | ||
| Generate and save terraform plans for creating the k8s cluster and document deis installation | Sam | Not started |
Issues during this sprint
Demos
Retrospective
Actions taken from last sprint
- [Maria] to remove simplify the Milestones, dropping the "Gate - 1" part