Final Schedule
- February 6 - Scaffolding began
- February 16 - Scaffolding finished and API began
- February 26 - Clearleft sends proposal
- March 3 - Clearleft sends contract
- March 5 - Contract is sent to legal
- March 26 - Legal sends contract to cbeard for signature
- April 6 - Justin uploads wireframes to Clearleft
- April 9 - May 8 - Clearleft design iterations
- April 22 - Contributions spec delivered to Clearleft
- April 28 - Clearleft implementation began
- April 30 - AMO 5.0.6 Kickoff meeting
- May 20 - Clearleft code "complete"
- June 9 - Launch
Time Spent
- Contract negotiation: 4 weeks
- Clearleft Design iterations: 4 weeks
- Clearleft Implementation: 3 weeks
- Mozilla WebDev (5.0.6): 6 weeks