Final Schedule

  • February 6 - Scaffolding began
  • February 16 - Scaffolding finished and API began
  • February 26 - Clearleft sends proposal
  • March 3 - Clearleft sends contract
  • March 5 - Contract is sent to legal
  • March 26 - Legal sends contract to cbeard for signature
  • April 6 - Justin uploads wireframes to Clearleft
  • April 9 - May 8 - Clearleft design iterations
  • April 22 - Contributions spec delivered to Clearleft
  • April 28 - Clearleft implementation began
  • April 30 - AMO 5.0.6 Kickoff meeting
  • May 20 - Clearleft code "complete"
  • June 9 - Launch

Time Spent

  • Contract negotiation: 4 weeks
  • Clearleft Design iterations: 4 weeks
  • Clearleft Implementation: 3 weeks
  • Mozilla WebDev (5.0.6): 6 weeks