Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: Feb 29, 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Richard Milewski
PROJECT WIKI: Air_Mozilla
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
2011-12-22 2011-12-22 Q2 N/A
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Initial dev meetings with Craig & Richard
    • Scope is larger than web dev thought
    • 70% systems work & improvement to content entry and scheduling / 30% re-design of airmozilla site
    • Met with fred to determine next steps
    • Prob will not be WordPress
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Develop Use Cases For Fred RM 2012-03-02 --
Identify Systems / Scope / Schedule FW/BS/RM 2012-03-07 --
Milestone Schedule & Approve BS/Team TBD ---
Create Any Housekeeping Bugs (QA/IT) BS TBD ---
Final Design TS 2012-03-12 --- In progress
Loop in WebDev BS 2012-02-27 --- Complete
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
Confirm New Dates/Timeline is OK RM high 2012-02-22 --
Digital Asset Manager Use/Not Use For Launch RM high 2012-02-30 --
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Acutal
Completion
Date
Bugzilla Status
Design
   Design Approved TS
   PSD Delivered TS
WebDev
   Release 1 Coding CC
   Release 1 Live CC
Content
   Content Entry RM
Privacy
   Release 1 Review Stacy
QA
   Release 1 Review SD
Security
   Release 1 Review
IT
   Setup Dev MZ
   Setup Staging MZ
   Setup Production MZ